Asakusa Rokku Redevelopment
First written in FY2017. 1 of 3 entries say "Advanced", first in FY2020. Latest entry: FY2021-Q1.
3entries
4years
0from disclosures
How it moved
Same theme, other companies
Redevelopment of the Asakusa Rokku Shochiku BuildingA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2021-Q1AchievedAnnual report
「The Asakusa Rokku Shochiku Building was completed in April, leasing began in May, and Nihon View Hotel Co., Ltd. was preparing to open a hotel.」
For the Asakusa Rokku redevelopment, the Asakusa Rokku Shochiku Building was completed and leasing began in May. Preparations for the hotel opening were also under way. - FY2020AdvancedAnnual report
「Asakusa Rokku redevelopment, Taito-ku, Tokyo, real estate business, rental building, ¥4,800 million, ¥3,590 million, internal funds and borrowings, June 2012, April 2020」
For the Asakusa Rokku redevelopment, the plan lists total planned investment of ¥4,800 million, ¥3,590 million already paid, and scheduled completion in April 2020, indicating the project’s progress and completion timing. - FY2017First statedAnnual report
「Asakusa Rokku redevelopment, rental building, planned investment (total): ¥3,000 million; construction started: June 2012; completion: December 2018」
The equipment plan for the redevelopment of a rental building in Asakusa Rokku lists total investment of ¥3,000 million, with completion scheduled for December 2018.