- FY2026AdvancedAnnual report
「In January 2026, Unit 1 of the Himeji Natural Gas Power Plant in Himeji, Hyogo Prefecture, with generating capacity of approximately 620,000 kW, was completed and began commercial operations. In May 2026, Unit 2, also with generating capacity of approximately 620,000 kW, was completed and began commercial operations.」
There was concrete progress in the development of new infrastructure for natural gas-fired power generation, with the completion and start of commercial operations of 2 units at the Himeji Power Station. - FY2022RestatedAnnual report
「We will expand the development of new energy infrastructure, including LNG terminals. We will also expand our engineering business by drawing on the expertise acquired through our business operations to propose solutions tailored to the needs of customers considering the introduction of LNG and other options.」
We continue to pursue the policy of expanding infrastructure development, including LNG terminals, and the engineering business for customers. - FY2019-Q1AdvancedAnnual report
「Effective 1 April 2018, we carried out organizational changes, including transferring the Engineering Department to the Gas Manufacturing and Power Generation Division and reorganizing that division as the Gas Manufacturing, Power Generation and Engineering Division.」
We implemented a specific organizational change by transferring the Engineering Department to the Gas Manufacturing and Power Generation Division and reorganizing the division to include engineering functions. - FY2018First statedAnnual report
「We will expand the development of new energy infrastructure, including LNG terminals, in Japan and overseas. We will also expand our engineering business by drawing on the expertise acquired through our business operations to propose solutions tailored to the needs of customers considering the introduction of LNG and other options.」
The company has identified the expansion of infrastructure development, including LNG terminals, and the engineering business through solutions tailored to customer needs as new challenges.