Periodic Inspection and Operations and Maintenance Risks at Biomass Power Plants

First written in FY2018. 7 of 14 entries say "Materialised", first in FY2021-Q1. Latest entry: 2026-08-06.

14entries
9years
6from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2018 – FY2020-Q1MaterialisedFY2021-Q1 – FY2025-H12018: 120182019: 120192020: 120202021: 220212022: 020222023: 120232024: 120242025: 120252026: 62026
Same theme, other companies
Risk of Unplanned Outages Due to Failures or Damage to Power Generation FacilitiesA theme 5 companies write about · 5 as a headwind · 0 as a tailwind

Renova moved to the "Worse" side of this theme in 2020, 3 years before the typical company in this theme (2023).

0 other companies' latest entry also says "Mitigated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026-H1MitigatedAnnual report

    「At 御前崎港バイオマスエナジー合同会社, inspections and repair work that had been under way since June 2025 were completed, and normal operations resumed on 10 October 2025.」

    At the Omaezaki Port biomass plant, inspections and repair work were completed and normal operations resumed on 10 October 2025. As the main stages of the scheduled inspection were carried out ahead of schedule, the scheduled inspection planned for January 2026 was no longer required.
  2. FY2025-H1MaterialisedAnnual report

    「Tokushima Tsuda Biomass Power Plant, owned by our consolidated subsidiary 徳島津田バイオマス発電所合同会社, is undergoing permanent remedial construction to make its facilities permanent for stable long-term operations.」

    The company stated that permanent remedial construction was under way at the Tokushima Tsuda biomass plant to support stable long-term operations.
  3. FY2024-Q1MaterialisedAnnual report

    「② Decrease in electricity sales revenue due to differences in the timing of scheduled maintenance and other factors at biomass power generation businesses, excluding ① above (△287)」

    Electricity sales revenue from the biomass power generation business decreased by ¥287 million due to differences in the timing of scheduled maintenance and other factors, and the impact of scheduled maintenance on results was reflected in the quarterly results.
  4. FY2021MaterialisedAnnual report

    「④ Decrease in URE's electricity sales due to an extended scheduled maintenance period and other factors (△145)」

    URE's electricity sales decreased by the equivalent of ¥145 million due to an extended scheduled maintenance period and other factors, and inspection and repair risks are reflected in the annual results.
  5. FY2021-Q3MaterialisedAnnual report

    「③ Decrease in URE's electricity sales due to an extended scheduled maintenance period and other factors (△117)」

    URE's electricity sales decreased by the equivalent of ¥117 million due to an extended scheduled maintenance period and other factors, and the risk of outages caused by scheduled inspections and repairs was reflected in the year-to-date results for the quarter.
  6. FY2021-Q1MaterialisedAnnual report

    「③ Decrease in URE's electricity sales due to an extended scheduled maintenance period and other factors (△142)」

    URE's electricity sales decreased by the equivalent of ¥142 million due to an extended scheduled maintenance period, and the risk of outages caused by scheduled inspections and repairs was reflected in the results for the quarter.
  7. FY2020-Q1Implementation of scheduled inspectionsAnnual report

    「URE conducted a scheduled inspection involving a planned shutdown in May 2019.」

    URE disclosed that it had conducted a scheduled inspection involving a planned shutdown. There was no mention of unanticipated repairs or an extended inspection period.
  8. FY2018First statedAnnual report

    「Scheduled plant inspections conducted around May each year are expected to involve several weeks of downtime. If repairs not anticipated in advance are identified during a scheduled inspection, the resulting extension of the downtime could reduce power generation and affect the group's business, results of operations and financial condition.」

    For operating biomass power plants, the company newly identified the risks of outages and lower power generation caused by scheduled inspections, unanticipated repairs, operating accidents and human error.
Moved together

"Unlimited, Uncompensated Output Curtailment for Solar, Wind and Biomass" moved the same way as this thread, in the same document, in 7 of its 14 moves.

744333★123456
  1. ★This thread
  2. 1Unlimited, Uncompensated Output Curtailment for Solar, Wind and Biomass7×
  3. 2Managing Reliance on Net Debt4×
  4. 3Interest-Bearing Debt, Financial Covenants and Funding Risk4×
  5. 4900 MW cumulative energy storage capacity target3×
  6. 5Recurring revenue from power plants in operation and development and operating businesses3×
  7. 6Expanding Business Partnerships with Leading Companies3×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
No upcoming earnings preview for Renova yet. It last moved in the Earnings presentation of 2026-08-06: "Mitigated".
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Periodic Inspection and Operations and Maintenance Risks at Biomass Power Plants | RENOVA,Inc. (9519) | Komori