Revenue Risk from Overseas FIT Schemes and Approved Capacity Allocations

First written in FY2022-Q2. 1 of 2 entries say "Reframed", first in FY2026. Latest entry: FY2026.

2entries
6years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2022-Q22021: 12022: 020222023: 020232024: 020242025: 020252026: 12026
Same theme, other companies
FIT Permit and Approval Risk in the Solar Power Generation BusinessA theme 5 companies write about · 5 as a headwind · 0 as a tailwind

Renova moved to the "Worse" side of this theme in 2026.

0 other companies' latest entry also says "Reframed".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2026ReframedAnnual report

    「In addition, for solar power projects in the country, the company is promoting development using the government’s Green Energy Auction Program (GEAP). If a successful bid under the program is delayed beyond the scheduled commercial operation start date, liquidated damages accrue daily. If the delay exceeds a specified period, the performance bond provided is forfeited in full and the bidder’s eligibility is revoked.」

    In addition to the existing risk concerning FIT capacity allocations for Philippine hydropower, the company added the potential channels of liquidated damages for delayed operations, forfeiture of performance bonds and revocation of bid eligibility under GEAP for Philippine solar power.
  2. FY2022-Q2First statedAnnual report

    「The company also invests in and participates in hydropower projects in the Republic of the Philippines (the “Philippines”). Under the FIT scheme for hydropower projects in the Philippines, an FIT price is approved and applied to projects that begin operations, and an upper limit is set on the aggregate capacity of hydropower projects eligible for FIT approval. The project in which the company invests and participates is currently under construction and is expected to fall within the applicable limit when operations begin. However, if the FIT allocation has reached its limit because of a delay in the start of operations or because other operators obtain FIT approval in excess of expectations by that time, the project in which the company invests and participates may be unable to obtain FIT approval. Even without FIT approval, electricity can be sold bilaterally to an offtaker or in the market, but if the company is forced to sell electricity below the FIT price, the Group’s operating results and financial position may be affected.」

    The company newly specified the risk that Vietnam onshore wind projects may be excluded from FIT eligibility because they exceed the deadline for starting operations, and that Philippine hydropower projects may be unable to obtain FIT approval because of the capacity limit or approvals obtained by other operators.
Moved together

None of this company's other threads moved the same way in the same document twice or more.