Participation in the Kiangan Hydropower Project in the Philippines
First written in FY2022-Q2. 1 of 4 entries say "Advanced", first in FY2022. Latest entry: FY2026.
No other company in this theme has enough history to compare yet.
- FY2026Update on project scale following design changesAnnual report
「KIANGAN MINI HYDRO CORPORATION Ifugao Province, Philippines 40.0% (equity method) 8.3」
Following the design change and downsizing of the Kiangan hydropower project, the output of the project under construction has been updated from 17.4MW to 8.3MW. - FY2024-Q3SoftenedAnnual report
「The project scale of the Kiangan hydropower project was reduced following a design change. Accordingly, the company recognized a full loss on the interest invested by its subsidiary.」
The Kiangan hydropower project was downsized following a design change, resulting in a full impairment loss being recognized on the equity interest. - FY2022AdvancedAnnual report
「List of projects under development ① Projects under construction KIANGAN MINI HYDRO CORPORATION Philippines Ifugao Province 40.0% (Equity method) 17.4 5.87 PHP April 2021 -」
The company specifically disclosed output of 17.4 MW, an equity interest of 40.0%, and the start of construction in April 2021 for the Kiangan hydropower project. - FY2022-Q2First statedAnnual report
「In July 2021, the Kiangan hydropower project under construction in Ifugao Province, the Republic of the Philippines, entered into financing-related agreements with financial institutions.」
The company disclosed for the first time that the Kiangan hydropower project in Ifugao Province, Republic of the Philippines, had progressed to the execution of loan-related agreements in July 2021 while under construction.