Execution of a loan agreement for the Minamiaso Yunodani geothermal power generation project
First written in FY2022-Q1. 2 of 6 entries say "Advanced", first in FY2022. Latest entry: FY2023.
No other company in this theme has enough history to compare yet.
- FY2023AchievedAnnual report
「株式会社南阿蘇湯の谷地熱 obtained a subsidy from JOGMEC (the Japan Organization for Metals and Energy Security), conducted surface and drilling surveys, began construction in June 2021, and began operations in March 2023.」
The Minami Aso Yunotani geothermal project began operations in March 2023 after surveys and the start of construction. - FY2023-Q3SoftenedAnnual report
「During the current consolidated fiscal year, the Minami Aso Yunotani Geothermal Power Plant and the Tokushima Tsuda Biomass Power Plant are scheduled to begin commercial operations in March 2023. (The scheduled commercial operation start date for Minami Aso Yunotani Geothermal changed from December 2022 to March 2023.)」
The scheduled commercial operation start date for the Minami Aso Yunotani Geothermal Power Plant changed from December 2022 to March 2023. - FY2023-Q2AdvancedAnnual report
「In October 2022, Minami-Aso Yunotani Geothermal Power Plant, Tokushima Tsuda Biomass Power Plant and Ishinomaki Hibarino Biomass Power Plant began trial operations. During the current consolidated fiscal year, Minami-Aso Yunotani Geothermal Power Plant was scheduled to commence commercial operations in December 2022, and Tokushima Tsuda Biomass Power Plant in March 2023.」
The company reconfirmed that the Minami Aso Yunotani Geothermal Power Plant began commissioning in October 2022 and was scheduled to begin commercial operations in December 2022. - FY2023-Q1RestatedAnnual report
「During the current consolidated fiscal year, Minami-Aso Yunotani Geothermal Power Generation was scheduled to commence operations in December 2022, and Tokushima Tsuda Biomass in March 2023.」
The company reconfirmed that the Minami Aso Yunotani geothermal power project was scheduled to begin operations in December 2022. - FY2022AdvancedAnnual report
「株式会社南阿蘇湯の谷地熱 obtained a subsidy from JOGMEC (the Japan Organization for Metals and Energy Security), conducted surface and drilling surveys, and began construction in June 2021.」
After conducting surveys and utilizing subsidies, Minami Aso Yunotani Geothermal began construction in June 2021 and disclosed a planned completion date of December 2022. - FY2022-Q1First statedAnnual report
「In June 2021, Minami Aso Yunodani Geothermal Co., Ltd., which operates a geothermal power business, entered into financing-related agreements with financial institutions.」
The company first disclosed in June 2021 that it had entered into loan-related agreements with financial institutions for the Minami Aso Yunotani geothermal power project.