Announced details
Electricity supply in Cambodia and hydropower generation using renewable energy
The project is expected to contribute to a stable supply of electricity in Cambodia. Specific quantified effects are Not disclosed.
A project in which the Company has held an equity interest since 2019. The Company has a 35-year power purchase and sales agreement with Electricité du Cambodge.
Cambodia's national electricity utility. Other information, including its location, representative, capital and year of establishment, is Not disclosed.
Pursat Province, Kingdom of Cambodia
Total investment: 240 MMUSD. The amount under the power purchase and sales agreement is Not disclosed.
The Company aims to strengthen its earnings base in the overseas power generation business, but the specific impact on earnings is Not disclosed.
The company does not address Offering price.
| Item | Details |
|---|---|
| Names of Products / Services Covered | Cambodian hydropower project (hydropower plant in Cambodia) |
| Counterparty | Electricité du Cambodge |
| Counterparty overview | Cambodia's national electricity utility. Other information, including its location, representative, capital and year of establishment, is Not disclosed. |
| Relationship with the Company | A project in which the Company has held an equity interest since 2019. The Company has a 35-year power purchase and sales agreement with Electricité du Cambodge. |
| Contract Value | Total investment: 240 MMUSD. The amount under the power purchase and sales agreement is Not disclosed. |
| Launch date | January 2027 (scheduled start of operations and commercial operations) |
| Applicable area | Electricity supply in Cambodia and hydropower generation using renewable energy |
| Location | Pursat Province, Kingdom of Cambodia |
| Location scale | Generation capacity: 80 MW; reservoir capacity: 1.2 billion m³ |
| Quantitative Effects | The project is expected to contribute to a stable supply of electricity in Cambodia. Specific quantified effects are Not disclosed. |
| Impact on Business Performance | The Company aims to strengthen its earnings base in the overseas power generation business, but the specific impact on earnings is Not disclosed. |
Items this document does not state (7)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.To advance reservoir filling using rainfall during the rainy season and target commissioning of the power generation facilities and the start of commercial operations in January 2027.