Construction and start of commercial operations at 豊後大野発電所
First written in FY2016. 15 of 16 entries say "Restated". Latest entry: FY2023-Q1.
2 other companies' latest entry also says "Restated".
- FY2023-Q1RestatedAnnual report
「EF-ON Shirakawa, EF-ON Bungo-Ono and the EF-ON Mibu Power Plant maintained high operating rates and operated smoothly.」
The filing continues to report the maintenance of high operating rates at the existing power plants, including 豊後大野 power plant. - FY2022-Q1RestatedAnnual report
「EF-ON Shirakawa, EF-ON Bungo-Ono and the EF-ON Mibu Power Plant maintained high operating rates and operated smoothly.」
The filing reports the continued high utilization of the existing power plants, including 豊後大野 power plant. - FY2021-Q2RestatedAnnual report
「Meanwhile, the エフオン豊後大野 and エフオン壬生 power plants maintained high operating rates and operated smoothly.」
The filing continues to report the maintenance of high operating rates at the existing power plants, including 豊後大野 power plant. - FY2021-Q1RestatedAnnual report
「The existing エフオン白河, エフオン日田 and エフオン豊後大野 power plants also maintained high operating rates and operated smoothly.」
The filing continues to state that the existing power plants, including 豊後大野 power plant, maintained high operating rates. - FY2020-Q3RestatedAnnual report
「The existing エフオン白河, エフオン日田 and エフオン豊後大野 power plants operated smoothly while maintaining high operating rates.」
The filing continues to state that the existing power plants, including エフオン豊後大野 power plant, maintained high operating rates and operated smoothly. - FY2020-Q1RestatedAnnual report
「Although エフオン白河, エフオン日田 and エフオン豊後大野 operated smoothly, net sales were below the same period of the previous year.」
The filing continues to state that the power plants, including 豊後大野 power plant, operated smoothly. - FY2019-Q3RestatedAnnual report
「In October, エフオン豊後大野 power plant had an unscheduled shutdown lasting 47 hours due to a failure of control-system equipment. During the other periods, all 3 wood biomass power plants maintained high operating rates and contributed to net sales.」
The filing continues to state that 豊後大野 power plant had a 47-hour unscheduled shutdown due to a control-system equipment failure, while the 3 plants maintained high operating rates during the other periods. - FY2019-Q2RestatedAnnual report
「In October, エフオン豊後大野 power plant had an unscheduled shutdown lasting 47 hours due to a failure of control-system equipment. During the other periods, all 3 wood biomass power plants maintained high operating rates and contributed to net sales.」
Regarding operations at 豊後大野 power plant after the start of commercial operations, the filing states that there was an unscheduled shutdown due to a control-system equipment failure, while the plant maintained a high operating rate during the other periods. - FY2018RestatedAnnual report
「The エフオン豊後大野 power plant, which began operations in the previous consolidated fiscal year, operated throughout the year and, together with the existing エフオン日田 and エフオン白河 power plants, maintained high operating rates.」
The filing continues to state that 豊後大野 power plant operated throughout the year and contributed to performance together with the existing power plants. - FY2018-Q3RestatedAnnual report
「In the third quarter of the current consolidated accounting period, the エフオン白河 and エフオン日田 power plants, which underwent scheduled maintenance during the second quarter, and the エフオン豊後大野 power plant, where scheduled maintenance is planned for the fourth quarter, operated at full capacity and steadily improved performance, making a significant contribution to both net sales and operating profit.」
The filing continues to state that the power generation business, including 豊後大野 power plant, operated at full capacity and contributed to net sales and operating profit, despite scheduled maintenance being conducted or planned. - FY2018-Q2RestatedAnnual report
「During the second quarter of the current consolidated accounting period, the 2 エフオン白河 and エフオン日田 power plants underwent scheduled maintenance. The other plants, including エフオン豊後大野, operated smoothly, making a significant contribution to both net sales and operating profit.」
The filing continues to state that the power generation business, including エフオン豊後大野 power plant, operated smoothly and contributed to net sales and operating profit. - FY2018-Q1RestatedAnnual report
「The エフオン豊後大野 wood biomass power plant, which began commercial operations in August of the previous year, maintained a high operating rate during the current quarter and made a significant contribution to both net sales and operating profit.」
The filing continues to state that 豊後大野 power plant maintained a high operating rate after beginning commercial operations and made a significant contribution to net sales and operating profit. - FY2017-Q3RestatedAnnual report
「Approximately 7 months after beginning operations, the wood biomass power plant in Bungo-Ono, Oita Prefecture, which is approximately 1.5 times the scale of the existing plants, continued to maintain a high operating rate and made a significant contribution to both net sales and operating profit.」
The filing states that 豊後大野 power plant maintained a high operating rate approximately 7 months after beginning operations and contributed to performance. - FY2017-Q2RestatedAnnual report
「Revenue and operating profit both increased substantially because the new woody biomass power plant in Bungo-Ono, Oita Prefecture, which commenced commercial operations in August, maintained high utilization.」
The Company continued to report high utilization and a contribution to results after the start of commercial operations at the Bungo-Ono plant. - FY2017-Q1RestatedAnnual report
「A new wood biomass power plant in Bungo-Ono, Oita Prefecture, began commercial operations in August.」
The filing reiterates that 豊後大野 power plant began commercial operations in August. - FY2016First statedAnnual report
「The Bungo-Ono Power Plant, the Group's third wood biomass power plant, which we had been developing in Bungo-Ono, Oita Prefecture, began commercial operations in August.」
The facility was scheduled for completion in August 2016, with an expected increase in transmitted electricity of approximately 120,000 MWh per year.