Construction and Start of Operations of the Central Java Coal-Fired IPP Project

First written in FY2016. 3 of 6 entries say "Restated". Latest entry: FY2022.

6entries
7years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2016 – FY20192016: 120162017: 120172018: 020182019: 120192020: 020202021: 120212022: 22022
Same theme, other companies
Construction and Commercial Operation Start of an Indonesia Batang Regency Coal-Fired IPPA theme 2 companies write about · 0 as a headwind · 2 as a tailwind

1 other company's latest entry also says "Advanced".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2022AdvancedAnnual report

    「We will also steadily carry out construction of the Central Java coal-fired power plant in Indonesia, our remaining major project, and work to further strengthen our earnings base.」

    Construction of the Central Java coal-fired power plant is continuing as the remaining major overseas project.
  2. FY2022-Q3RestatedAnnual report

    「Assets increased by ¥55.1 billion from the end of the previous consolidated fiscal year to ¥2,897.0 billion, mainly due to progress on construction of the Central Java coal-fired power plant in Indonesia and the Jackson gas-fired power plant in the United States.」

    Construction of the Central Java coal-fired power plant continued to progress and was recorded as a factor increasing assets.
  3. FY2022-Q1AdvancedAnnual report

    「Assets increased by ¥58.2 billion from the end of the previous fiscal year to ¥2,900.2 billion, due in part to the impact of the weaker yen and progress in construction of the Central Java coal-fired power plant in Indonesia and the Jackson gas-fired power plant in the United States.」

    Progress on construction of the Central Java coal-fired power plant was recorded as a ¥58.2 billion factor increasing assets from the end of the previous consolidated fiscal year.
  4. FY2019RestatedAnnual report

    「Construction of the Central Java coal-fired power plant in Indonesia, currently under construction, will proceed steadily under the construction plan. The plant has a capacity of 2,000 MW and is a joint project with PT. ADARO POWER and ITOCHU Corporation.」

    The policy has been reconfirmed to proceed with the 2,000 MW Central Java coal-fired power plant project under construction in accordance with the construction plan.
  5. FY2017RestatedAnnual report

    「For this project, land acquisition and the execution of loan agreements with the lending bank syndicate have been completed. Going forward, the project will proceed under the construction plan with the aim of commencing operations in June 2020 for Unit 1 and December of the same year for Unit 2.」

    The Central Java coal-fired IPP project is reiterated as having completed land acquisition and loan agreements, with planned commencement dates for Units 1 and 2.
  6. FY2016First statedAnnual report

    「For this project, land acquisition and the execution of loan agreements with the lending bank syndicate have been completed. Construction will proceed under the construction plan with the aim of commencing operations in June 2020 for Unit 1 and December of the same year for Unit 2.」

    For the 2,000 MW joint project, the completion of land acquisition and loan agreement execution is stated, along with the planned commencement dates for Units 1 and 2.
Moved together

"Growth in overseas power generation operations and expansion of overseas equity-method generation capacity" moved the same way as this thread, in the same document, in 2 of its 6 moves.

222★123
  1. ★This thread
  2. 1Growth in overseas power generation operations and expansion of overseas equity-method generation capacity2×
  3. 2Expansion of Renewable Energy Deployment2×
  4. 3Expansion of the Power Generation Business in the United States2×

★ is this thread; numbers match the list above. The number on a line is how many documents both moved the same way in; lines between the other threads count the documents they moved together in too. Threads that move together often sit closer.

When this could move next
Electric Power Development's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Construction and Start of Operations of the Central Java Coal-Fired IPP Project | Electric Power Development Co.,Ltd. (9513) | Komori