Hokkaido Electric Power Company (9509) · InitiativeAchieved
Construction of the Shintoku Hydroelectric Power Station
First written in FY2022. 1 of 2 entries say "Achieved", first in FY2023-Q1. Latest entry: FY2023-Q1.
2entries
1years
0from disclosures
How it moved
Same theme, other companies
Expansion of Hydropower Facilities and Generation OutputA theme 4 companies write about · 0 as a headwind · 4 as a tailwind
0 other companies' latest entry also says "Achieved".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2023-Q1AchievedAnnual report
「Hydropower Shintoku (new facility) 23,100 April 2019 June 2022」
The 23,100kW Shintoku Hydroelectric Power Station began operations in June 2022, completing the planned construction of the new facility. - FY2022First statedAnnual report
「Hydropower Shintoku (new facility) 23,100 April 2019 June 2022」
The plan calls for construction of the 23,100kW Shintoku Hydroelectric Power Station to begin in April 2019 and operations to begin in June 2022.