The Kansai Electric Power Company (9503) · InitiativeRestated
LNG Fuel Conversion for Units 1 and 3 at the Aioi Power Station
First written in FY2017-Q2. 1 of 2 entries say "Restated". Latest entry: FY2017-Q3.
2entries
2years
0from disclosures
How it moved
Same theme, other companies
LNG Fuel Conversion for Units 1 and 3 at the Aioi Power StationA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2017-Q3RestatedAnnual report
「Steam power generation facilities Aioi Power Station, Aioi City, Hyogo Prefecture (Units 1 and 3) 750,000 (Fuel before change) heavy oil, crude oil (Fuel after change) heavy oil, crude oil, LNG (Unit 1) May 2016 (Unit 3) August 2016」
The completed facility upgrade involving the addition of LNG to the fuel mix for Units 1 and 3 at Aioi Power Station is reiterated. - FY2017-Q2First statedAnnual report
「Steam power generation facilities Aioi Power Station, Aioi City, Hyogo Prefecture (Units 1 and 3) 750,000 (Fuel before change) heavy oil, crude oil (Fuel after change) heavy oil, crude oil, LNG (Unit 1) May 2016 (Unit 3) August 2016」
The text states that LNG was added to the fuel mix for Units 1 and 3 at Aioi Power Station as part of a completed facility upgrade.