Planned Reactor Startup and Commencement of Adjustment Operation at Mihama Nuclear Power Station Unit 3 (Water Dripping from Around the Air Vent Valve on the Outlet Piping of the 6A High-Pressure Feedwater Heater Normal Water-Level Control Valve)

After completing the investigation into the cause and measures including replacement of the piping, Mihama Nuclear Power Station Unit 3 is scheduled to start up on 10 October 2026 and resume adjustment operation. Full operation, following completion of the comprehensive load performance inspection, is scheduled for 4 November.

Worth reading
49Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Mixed performance
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Conditional
How definitive the wording is.

Planned Reactor Startup and Commencement of Adjustment Operation at Mihama Nuclear Power Station Unit 3 (Water Dripping from Around the Air Vent Valve on the Outlet Piping of the 6A High-Pressure Feedwater Heater Normal Water-Level Control Valve)

Subject Entity

The Kansai Electric Power Company,Incorporated Mihama Nuclear Power Station Unit 3

Target Locations / Products

Around the air vent valve on the outlet piping of the 6A high-pressure feedwater heater's normal water-level control valve at Mihama Nuclear Power Station Unit 3

OccurrenceAround 15:45 on 17 September 2026
Same day
Awareness or receipt of noticeAround 15:45 on 17 September 2026
This disclosure10/09/2026
Cause

It is presumed that, when the insulation and exterior panels were installed during construction work in 2010, the exterior panel directly above the penetration was installed upside down. Rainwater subsequently entered through the joint in the exterior panel, causing external corrosion of the piping to progress until it penetrated the pipe wall.

Company response

Suspended operations

Reactor operation at Mihama Nuclear Power Station Unit 3

Scheduled resumption date

Reactor startup and criticality: 10 October 2026; commencement of adjustment operation: 10 October 2026; resumption of full operation (completion of the comprehensive load performance inspection): 4 November 2026

Measures to prevent recurrence

The piping was replaced with stainless steel piping, and the precautions concerning the installation direction of exterior panels were clarified in the "Repair and Maintenance Work Guide."

Outlook

The reactor is scheduled to start up on 10 October 2026, with adjustment operation scheduled to begin on the same day. Resumption of full operation (completion of the comprehensive load performance inspection) is scheduled for 4 November 2026.

Event that occurred
ItemDetails
Event namePlanned Reactor Startup and Commencement of Adjustment Operation at Mihama Nuclear Power Station Unit 3 (Water Dripping from Around the Air Vent Valve on the Outlet Piping of the 6A High-Pressure Feedwater Heater Normal Water-Level Control Valve)
Date of occurrenceAround 15:45 on 17 September 2026
Date recognized / date notice receivedAround 15:45 on 17 September 2026
Subject EntityThe Kansai Electric Power Company,Incorporated Mihama Nuclear Power Station Unit 3
Target Locations / ProductsAround the air vent valve on the outlet piping of the 6A high-pressure feedwater heater's normal water-level control valve at Mihama Nuclear Power Station Unit 3
CauseIt is presumed that, when the insulation and exterior panels were installed during construction work in 2010, the exterior panel directly above the penetration was installed upside down. Rainwater subsequently entered through the joint in the exterior panel, causing external corrosion of the piping to progress until it penetrated the pipe wall.
Suspended operationsReactor operation at Mihama Nuclear Power Station Unit 3
Scheduled resumption dateReactor startup and criticality: 10 October 2026; commencement of adjustment operation: 10 October 2026; resumption of full operation (completion of the comprehensive load performance inspection): 4 November 2026
Measures to prevent recurrenceThe piping was replaced with stainless steel piping, and the precautions concerning the installation direction of exterior panels were clarified in the "Repair and Maintenance Work Guide."
OutlookThe reactor is scheduled to start up on 10 October 2026, with adjustment operation scheduled to begin on the same day. Resumption of full operation (completion of the comprehensive load performance inspection) is scheduled for 4 November 2026.
Items this document does not state (15)
Amount of Impact on Business PerformanceAccounting period in which recognizedImpact on Earnings ForecastType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionInvestigation structureDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the changePlanned follow-up disclosure

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

It is presumed that, because the exterior panel was installed upside down during construction work in 2010, rainwater entered through the joint, causing external corrosion of the piping to progress until it penetrated the pipe wall.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Planned Reactor Startup and Commencement of Adjustment Operation at Mihama Nuclear Power Station Unit 3 (Water Dripping from Around the Air Vent Valve on the Outlet Piping of the 6A High-Pressure Feedwater Heater Normal Water-Level Control Valve) | The Kansai Electric Power Company,Incorporated (9503) timely disclosure | Komori