Komori
Occurring Fact9503The Kansai Electric Power Company,IncorporatedElectricity and gas

Errors in Calculating Electricity Tariff Costs in the Regulated Sector

The Kansai Electric Power Company, Incorporated announced that it had incorrectly determined the discount applicable to generation-side charges when calculating the regulated tariff cost in April 2024, resulting in the cost being overstated by approximately ¥14 million over 3 years, or approximately ¥5 million for a single year. The impact on customer charges is expected to be no more than ¥1 per contract type per month, and the company will consider how to make refunds.

Worth reading
43Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Deterioration
Direction inferred from the company’s description.
Scale
14
¥ million (over 3 years; approximately ¥5 million for a single year)
Wording
Conditional
How definitive the wording is.

Errors in Calculating Electricity Tariff Costs in the Regulated Sector

Subject Entity

The Kansai Electric Power Company,Incorporated

Target Locations / Products

Electricity charges in the regulated sector, specified retail supply terms, certain power plants, and generation-side charges

Occurrence1 April 2024 (the date on which the specified retail supply terms took effect; the calculation error occurred when calculating the cost for April 2024)
This disclosure09/17/2026
Cause

The discount rate applicable to generation-side charges was incorrectly determined in part because a receiving voltage of 154kV was classified as exceeding the standard voltage of 140kV, although the 154kV in question was a nominal voltage, not a standard voltage.

Amount of Impact on Business Performance

The change in regulated tariff cost was an overstatement of approximately ¥14 million over 3 years, or approximately ¥5 million for a single year. The impact on customer charges is expected to be no more than ¥1 per contract type per month. The income statement line item is Not disclosed.

Related procedures

Court or authority

Minister of Economy, Trade and Industry (identified as the recipient of the notification of changes to the specified retail supply terms)

Company response

Measures to prevent recurrence

We will work to prevent recurrence.

Outlook

We will consider how to make refunds to customers and work to prevent recurrence.

Event that occurred
ItemDetails
Event nameErrors in Calculating Electricity Tariff Costs in the Regulated Sector
Date of occurrence1 April 2024 (the date on which the specified retail supply terms took effect; the calculation error occurred when calculating the cost for April 2024)
Subject EntityThe Kansai Electric Power Company,Incorporated
Target Locations / ProductsElectricity charges in the regulated sector, specified retail supply terms, certain power plants, and generation-side charges
CauseThe discount rate applicable to generation-side charges was incorrectly determined in part because a receiving voltage of 154kV was classified as exceeding the standard voltage of 140kV, although the 154kV in question was a nominal voltage, not a standard voltage.
Amount of Impact on Business PerformanceThe change in regulated tariff cost was an overstatement of approximately ¥14 million over 3 years, or approximately ¥5 million for a single year. The impact on customer charges is expected to be no more than ¥1 per contract type per month. The income statement line item is Not disclosed.
Court or authorityMinister of Economy, Trade and Industry (identified as the recipient of the notification of changes to the specified retail supply terms)
Measures to prevent recurrenceWe will work to prevent recurrence.
OutlookWe will consider how to make refunds to customers and work to prevent recurrence.
Items this document does not state (16)
Date recognized / date notice receivedAccounting period in which recognizedImpact on Earnings ForecastType of litigation or proceedingPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionSuspended operationsScheduled resumption dateInvestigation structureDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the changePlanned follow-up disclosure

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The discount rate for generation-side charges was incorrectly determined because a receiving voltage of 154kV was classified as exceeding the standard voltage of 140kV. In fact, the stated 154kV was a nominal voltage, not a standard voltage.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Errors in Calculating Electricity Tariff Costs in the Regulated Sector | The Kansai Electric Power Company,Incorporated (9503) timely disclosure | Komori