Occurring Fact9503The Kansai Electric Power Company,IncorporatedElectricity and gas

Regarding the Automatic Shutdown of the Reactor at Ohi Nuclear Power Station Unit 3

At 23:56 on 8 August 2026, a “loss of field” alarm was activated at Ohi Nuclear Power Station Unit 3, automatically shutting down the generator and reactor. The cause is under investigation, and there is reportedly no impact from radiation on the surrounding environment.

Worth reading
33Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Deterioration
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Avoiding a definitive answer
How definitive the wording is.

Regarding the Automatic Shutdown of the Reactor at Ohi Nuclear Power Station Unit 3

Subject Entity

The Kansai Electric Power Company,Incorporated (reporting company)

Target Locations / Products

Ohi Nuclear Power Station Unit 3 (operating at constant rated thermal output)

Occurrence23:56 on 8 August 2026
This disclosure08/10/2026
Cause

The “loss of field” alarm was activated. The root cause is currently under investigation.

Impact on Earnings Forecast

If any matters requiring disclosure, including any impact on business performance, are identified, we will promptly announce them.

Company response

Suspended operations

The generator automatically shut down, followed by the automatic shutdown of the reactor.

Outlook

We will investigate the cause and promptly provide notice if any matters requiring disclosure, including any impact on earnings, are identified.

Planned follow-up disclosure

We will promptly provide notice if any matters requiring disclosure are identified.

Event that occurred
ItemDetails
Event nameRegarding the Automatic Shutdown of the Reactor at Ohi Nuclear Power Station Unit 3
Date of occurrence23:56 on 8 August 2026
Subject EntityThe Kansai Electric Power Company,Incorporated (reporting company)
Target Locations / ProductsOhi Nuclear Power Station Unit 3 (operating at constant rated thermal output)
CauseThe “loss of field” alarm was activated. The root cause is currently under investigation.
Impact on Earnings ForecastIf any matters requiring disclosure, including any impact on business performance, are identified, we will promptly announce them.
Suspended operationsThe generator automatically shut down, followed by the automatic shutdown of the reactor.
OutlookWe will investigate the cause and promptly provide notice if any matters requiring disclosure, including any impact on earnings, are identified.
Planned follow-up disclosureWe will promptly provide notice if any matters requiring disclosure are identified.
Items this document does not state (16)
Date recognized / date notice receivedAmount of Impact on Business PerformanceAccounting period in which recognizedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionScheduled resumption dateInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The generator automatically shut down when the “loss of field” alarm was activated, and the reactor automatically shut down as a result. The root cause is currently under investigation.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Regarding the Automatic Shutdown of the Reactor at Ohi Nuclear Power Station Unit 3 | The Kansai Electric Power Company,Incorporated (9503) timely disclosure | Komori