Komori
Statutory disclosure document9502Chubu Electric Power Company,IncorporatedElectricity and gas

Withdrawal of applications for permission to modify the installation of Units 3 and 4 at the Hamaoka Nuclear Power Station and related matters

It was decided to withdraw the applications related to the new regulatory standards, including the applications for approval of changes to the reactor installations, for Units 3 and 4 of the Hamaoka Nuclear Power Station. Once preparations are complete, the withdrawal will be submitted to the Nuclear Regulation Authority.

Worth reading
69In focus
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Deterioration
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Conditional
How definitive the wording is.

Decision and Details

Extraordinary Board of Directors meeting

Withdrawal of the applications for approval of changes to the reactor installations and other applications related to the new regulatory standards for Units 3 and 4 of the Hamaoka Nuclear Power Station

Decision14 September 2026
ImplementationScheduled to be submitted to the Nuclear Regulation Authority once preparations are complete
Going forwardOnce preparations are complete, the withdrawal will be submitted to the Nuclear Regulation Authority. Any matters requiring disclosure will be announced promptly.
Quantity / scaleHamaoka Nuclear Power Station Units 3 and 4; 3 types of applications
Reason

Based on the contents of the investigation report issued by the Investigation Committee, it was determined that maintaining the previous applications would not be appropriate given the serious doubts regarding the reliability of the application materials and the subsequent responses to the review.

Impact on Business Performance

The impact on current and future consolidated results is undetermined at this time

Decision and Details
ItemDetails
Matter CoveredWithdrawal of the applications for approval of changes to the reactor installations and other applications related to the new regulatory standards for Units 3 and 4 of the Hamaoka Nuclear Power Station
Decision-Making BodyExtraordinary Board of Directors meeting
Decision Date14 September 2026
Implementation DateScheduled to be submitted to the Nuclear Regulation Authority once preparations are complete
Quantity / scaleHamaoka Nuclear Power Station Units 3 and 4; 3 types of applications
Impact on Business PerformanceThe impact on current and future consolidated results is undetermined at this time
ReasonBased on the contents of the investigation report issued by the Investigation Committee, it was determined that maintaining the previous applications would not be appropriate given the serious doubts regarding the reliability of the application materials and the subsequent responses to the review.
Governing RuleAlthough it is stated that these are applications related to the new regulatory standards, the provision serving as the basis for the withdrawal is Not disclosed
Related previous disclosures5 January 2026 notice, “Inappropriate Matter Concerning the Development of Design-Basis Ground Motion in the Review of Compliance with the New Regulatory Standards for the Hamaoka Nuclear Power Station”
Future plansOnce preparations are complete, the withdrawal will be submitted to the Nuclear Regulation Authority. Any matters requiring disclosure will be announced promptly.
Items this document does not state (2)
Period CoveredAmount

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

Based on the investigation report issued by the Investigation Committee, serious doubts have arisen regarding the reliability of the application materials and the subsequent responses to the review, and it was determined that maintaining the previous applications would not be appropriate.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Withdrawal of applications for permission to modify the installation of Units 3 and 4 at the Hamaoka Nuclear Power Station and related matters | Chubu Electric Power Company,Incorporated (9502) timely disclosure | Komori