Statutory disclosure document9502Chubu Electric Power Company,IncorporatedElectricity and gas

Publication of the Investigation Report on the Inappropriate Matter Concerning the Development of Design-Basis Earthquake Ground Motion in the Review of Compliance with the New Regulatory Requirements for the Hamaoka Nuclear Power Station (2/3)

The Special Investigation Committee published an Investigation Report (publicly disclosed version) on inappropriate conduct by Chubu Electric Power related to the formulation of design-basis ground motion and other matters at the Hamaoka Nuclear Power Station, including its investigation findings, analysis of the causes, and recommendations for measures to prevent recurrence.

Worth reading
78Important
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Deterioration
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Conditional
How definitive the wording is.

Decision and Details

Board of Directors (resolution to establish the special investigation committee)

Inappropriate conduct related to the formulation of design-basis ground motions in the review of Hamaoka Nuclear Power Station's compliance with New Regulatory Requirements

Decision5 January 2026
Period CoveredInvestigation period: 5 January 2026 to 11 September 2026
Implementation11 September 2026 (publication date of the publicly disclosed version of the Investigation Report; actual date)
Going forwardChubu Electric Power will implement measures to prevent recurrence based on the contents of this report, and will also verify the facts and take any additional measures necessary with respect to similar cases outside the scope of the investigation.
Quantity / scale87 interviews and other sessions in total, 54 people covered, 28 people subject to digital forensics, 6,296 items reviewed, 4,221 people surveyed and 3,796 responses, 36 committee meetings
Reason

To investigate the facts and causes of the subject matter and consider measures to prevent recurrence while ensuring transparency and fairness.

Impact on Business Performance

The subject matter is considered capable of having a serious impact on the review for conformity with new regulatory requirements and potentially shaking the foundations of the nuclear energy business. The specific amount of the impact on financial results is Not disclosed.

Decision and Details
ItemDetails
Matter CoveredInappropriate conduct related to the formulation of design-basis ground motions in the review of Hamaoka Nuclear Power Station's compliance with New Regulatory Requirements
Decision-Making BodyBoard of Directors (resolution to establish the special investigation committee)
Decision Date5 January 2026
Implementation Date11 September 2026 (publication date of the publicly disclosed version of the Investigation Report; actual date)
Period CoveredInvestigation period: 5 January 2026 to 11 September 2026
Quantity / scale87 interviews and other sessions in total, 54 people covered, 28 people subject to digital forensics, 6,296 items reviewed, 4,221 people surveyed and 3,796 responses, 36 committee meetings
Impact on Business PerformanceThe subject matter is considered capable of having a serious impact on the review for conformity with new regulatory requirements and potentially shaking the foundations of the nuclear energy business. The specific amount of the impact on financial results is Not disclosed.
ReasonTo investigate the facts and causes of the subject matter and consider measures to prevent recurrence while ensuring transparency and fairness.
Governing RuleArticles 43-3-5 and other provisions of the Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors; Article 67, Paragraph 1 of the Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors; Article 106, Paragraph 3 of the Electricity Business Act; Japan Federation of Bar Associations, Guidelines for Third-Party Committees in Corporate Misconduct
Related previous disclosuresChubu Electric Power press release dated 5 January 2026 (press release concerning the subject matter); Board of Directors resolution dated 5 January 2026
Future plansChubu Electric Power will implement measures to prevent recurrence based on the contents of this report, and will also verify the facts and take any additional measures necessary with respect to similar cases outside the scope of the investigation.
Items this document does not state (1)
Amount

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

Because the subject matter could have a serious impact on the review for conformity with new regulatory requirements, could severely undermine stakeholders' trust in Chubu Electric Power's nuclear energy business, and could potentially shake the foundations of that business, making it necessary to investigate the facts, causes, and measures to prevent recurrence while ensuring transparency and fairness.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Publication of the Investigation Report on the Inappropriate Matter Concerning the Development of Design-Basis Earthquake Ground Motion in the Review of Compliance with the New Regulatory Requirements for the Hamaoka Nuclear Power Station (2/3) | Chubu Electric Power Company,Incorporated (9502) timely disclosure | Komori