Funding from the Nuclear Damage Compensation and Decommissioning Facilitation Corporation
Tokyo Electric Power Company Holdings,Incorporated
Compensation payments expected to be made by the end of August 2026 were expected to exceed the total amount of compensation funds and funding disbursements received to date.
Related procedures
Nuclear Damage Compensation and Decommissioning Facilitation Corporation
While receiving financial assistance from NDF, the company will continue to provide compensation with the needs of those affected by the nuclear accident in mind, through to the very last person.
| Item | Details |
|---|---|
| Event name | Funding from the Nuclear Damage Compensation and Decommissioning Facilitation Corporation |
| Date of occurrence | 23 July 2026 (date funding was received) |
| Subject Entity | Tokyo Electric Power Company Holdings,Incorporated |
| Cause | Compensation payments expected to be made by the end of August 2026 were expected to exceed the total amount of compensation funds and funding disbursements received to date. |
| Court or authority | Nuclear Damage Compensation and Decommissioning Facilitation Corporation |
| Outlook | While receiving financial assistance from NDF, the company will continue to provide compensation with the needs of those affected by the nuclear accident in mind, through to the very last person. |
Items this document does not state (19)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The company had requested its 171st funding disbursement because compensation payments expected to be made by the end of August 2026 were expected to exceed the total amount of compensation funds and funding disbursements received to date.