Items stated in the management plan
Partially revisedThe revision reflects the increase in estimated costs associated with the discharge of ALPS-treated water, the extension of the estimated periods and increase in payment results for business losses, reputational damage, indirect losses and other items, as well as the increased acceptance of claims for certain decontamination and other costs and the resulting growth in predictability as related projects have progressed.
| Item | Details |
|---|---|
| Plan name | Fifth Comprehensive Special Business Plan (Fifth Comprehensive Special Plan) |
| Progress against the plan | Partially revised |
| Reason for revision or withdrawal | The revision reflects the increase in estimated costs associated with the discharge of ALPS-treated water, the extension of the estimated periods and increase in payment results for business losses, reputational damage, indirect losses and other items, as well as the increased acceptance of claims for certain decontamination and other costs and the resulting growth in predictability as related projects have progressed. |
| Publication date | 31 March 2026 |
Items this document does not state (21)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The increase in estimated costs associated with the discharge of ALPS-treated water, the extension of the estimated periods and increase in payment results for business losses, reputational damage and indirect losses, and the increased acceptance of claims for certain decontamination and other costs, together with growing predictability as related projects have progressed.