Start of operations at the Miki Biomass Factory
First written in FY2024-Q1. 1 of 3 entries say "Advanced", first in FY2024-Q2. Latest entry: FY2024-Q3.
No other company in this theme has enough history to compare yet.
- FY2024-Q3AchievedAnnual report
「The increase in acceptance volume resulting from the Miki Biomass Factory, which began full-scale operations in October 2023 after starting operations in May 2023」
The factory reached full-scale operations in October 2023 and contributed to higher acceptance volume. - FY2024-Q2AdvancedAnnual report
「We are making steady progress with test operations at the Miki Biomass Factory, which began operations in May 2023, toward full-scale operations from October 2023」
The facility progressed from start-up and preparation to testing toward full-scale operations in October 2023. - FY2024-Q1First statedAnnual report
「In May 2023, the Miki Biomass Factory began operations at our Miki Recycling Center. The facility is a thermal treatment facility with a capacity of 440 tonnes per day that co-fires biomass resources and various types of waste. It will also contribute to advancing resource recycling, and we are establishing the systems needed for an early start of full-scale operations.」
A 440-tonne-per-day thermal treatment facility began operations in May 2023, with preparations underway for full-scale operations.