Daiei Kankyo (9336) · InitiativeAchieved
Expansion of the Gobo Recycling Center Final Disposal Facility
First written in FY2023-Q3. 3 of 4 entries say "Achieved", first in 2026-03-24. Latest entry: FY2026.
4entries
4years
2from disclosures
How it moved
Same theme, other companies
Expansion and Commencement of Operations of the Landfill at Gobo Recycling CenterA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2026AchievedAnnual report
「In October 2025, the Phase 2 controlled final disposal site at our Gobo Recycling Center began service.」
The previously planned Phase 2 controlled final disposal site at the Gobo Recycling Center began service. - FY2023-Q3First statedAnnual report
「At our Gobo Recycling Center in Gobo, Wakayama Prefecture, Wakayama Prefecture issued a permit in December 2022 for the installation of an industrial-waste treatment facility to expand the controlled final disposal site by approximately 1.35 million m3, and we are preparing for an early start of service.」
Obtaining approval to expand capacity by approximately 1.35 million m3 was stated as progress before the start of service.