Announced details
Waste treatment, resource recycling, incineration, recycling
Daiei Kankyo Co.,Ltd. serves as the representative company, 株式会社川崎技研 as a member company, and 株式会社桑原組 as a cooperating company in the corporate group formed as the contractor. Takashima City is the project owner.
Takashima City, Shiga Prefecture. The mayor is Imashiro Katsuhiro (今城 克啓).
Tanaka, Adogawa-cho, Takashima City, Shiga Prefecture
¥28.7287 billion (including consumption and local consumption taxes)
The company does not address Offering price / Impact on Business Performance.
Takashima City’s New Waste Treatment Facility Development Master Plan, formulated in February 2024
| Item | Details |
|---|---|
| Names of Products / Services Covered | (provisional name) Takashima City New Waste Treatment Facility Development and Operation Project |
| Counterparty | Takashima City (Mayor: Imashiro Katsuhiro (今城 克啓)) |
| Counterparty overview | Takashima City, Shiga Prefecture. The mayor is Imashiro Katsuhiro (今城 克啓). |
| Relationship with the Company | Daiei Kankyo Co.,Ltd. serves as the representative company, 株式会社川崎技研 as a member company, and 株式会社桑原組 as a cooperating company in the corporate group formed as the contractor. Takashima City is the project owner. |
| Contract Value | ¥28.7287 billion (including consumption and local consumption taxes) |
| Launch date | Operation and management services for the incineration facility and other facilities are scheduled to begin on 1 March 2030. Operations at the recycling facility and other facilities are scheduled to begin in April 2032. Design and construction are scheduled to begin in December 2026. |
| Applicable area | Waste treatment, resource recycling, incineration, recycling |
| Location | Tanaka, Adogawa-cho, Takashima City, Shiga Prefecture |
| Location scale | Incineration facility: 39 tonnes/24 hours (19.5 tonnes/24 hours × 2 furnaces); recycling facility: 12 tonnes/5 hours (shredding processing: 7 tonnes/5 hours; resource processing: 5 tonnes/5 hours) |
| Source | Takashima City’s New Waste Treatment Facility Development Master Plan, formulated in February 2024 |
Items this document does not state (8)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The project involves the new construction of incineration and recycling facilities based on Takashima City’s New Waste Treatment Facility Development Master Plan, together with the comprehensive design, construction and long-term operation and management of the facilities. The Group intends to leverage its operational track record and expertise in managing general waste treatment facilities.