Adoption of the NAIAS Safety System at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
First written in FY2018-Q1. 3 of 6 entries say "Restated". Latest entry: FY2020-Q2.
No other company in this theme has enough history to compare yet.
- FY2020-Q2AdvancedAnnual report
「Meanwhile, we completed the design work required for installation in the actual facility of the Nias sprinkler fire-extinguishing system, which we had continued to implement as a safety measure at nuclear power stations. The work will now move to the next stage, creating expectations for capturing demand in the energy-related market.」
For Nias at the Kashiwazaki-Kariwa and other nuclear power stations, the company states that the design work required for installation in the actual facility has been completed and that the project is moving to the next stage. - FY2019-Q2RestatedAnnual report
「The Nias sprinkler fire-extinguishing system has been selected for the safety measures at Tokyo Electric Power Company Holdings,Incorporated's Kashiwazaki-Kariwa Nuclear Power Station, and work toward installation in the actual facility is ongoing.」
Following its selection at the Kashiwazaki-Kariwa Nuclear Power Station, work toward installation in the actual facility is continuing. - FY2018RestatedAnnual report
「Nias has been selected for the safety measures at a nuclear power station operated by Tokyo Electric Power Company Holdings,Incorporated. Work toward installation in the actual facility is still ongoing, and the project is making steady progress.」
Work toward installation in the actual facility has continued following selection, but completion of the installation is not stated. - FY2018-Q3RestatedAnnual report
「Nias has been selected for the safety measures at Tokyo Electric Power Company Holdings,Incorporated's Kashiwazaki-Kariwa Nuclear Power Station. Work toward installation in the actual facility is still ongoing, and the project is making steady progress.」
Work toward installation in the actual facility at the Kashiwazaki-Kariwa Nuclear Power Station is continuing and progressing, but no new completion stage is indicated. - FY2018-Q2AdvancedAnnual report
「The Nias sprinkler fire-extinguishing system has been selected for the safety measures at Tokyo Electric Power Company Holdings,Incorporated's Kashiwazaki-Kariwa Nuclear Power Station, and work toward installation in the actual facility is ongoing. Accordingly, an order is expected after the system specifications are finalized.」
The project has progressed from selection to the stage of continuing work toward installation in the actual facility, and an order is expected after the specifications are finalized. - FY2018-Q1First statedAnnual report
「As a result, the Nias sprinkler fire-extinguishing system has now been selected for the safety measures at Tokyo Electric Power Company Holdings,Incorporated's Kashiwazaki-Kariwa Nuclear Power Station, and we have taken steps in preparation for the future.」
The company states that Nias was selected for the safety measures at Tokyo Electric Power Company Holdings,Incorporated's Kashiwazaki-Kariwa Nuclear Power Station as a result of promotional activities.