Notice Regarding the Impact of the “2026 Kumamoto Earthquake” (Update on Previously Disclosed Matters)

Service on the Kyushu Shinkansen between Kumamoto and Shin-Minamata stations, which has been suspended due to the Kumamoto earthquake, is expected to resume from 18 September. Service on the Kagoshima Main Line between Uto and Yatsushiro stations is expected to resume around mid-October. The amount of damage caused by the earthquake and its impact on financial results remain under investigation.

Worth reading
51Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Mixed performance
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Avoiding a definitive answer
How definitive the wording is.

Impact of the “Reiwa 8 Kumamoto Earthquake”

Subject Entity

Kyushu Railway Company

Target Locations / Products

Kyushu Shinkansen (Kumamoto Station–Shin-Minamata Station); Kagoshima Main Line (Uto Station–Yatsushiro Station)

Occurrence28 July 2026
This disclosure08/27/2026
Cause

The 2026 Kumamoto Earthquake, which occurred on 28 July 2026

Amount of Impact on Business Performance

The amount of damage and the impact on financial results remain under investigation. The amount has not yet been determined.

Impact on Earnings Forecast

The amount of damage and the impact on financial results remain under investigation. If timely disclosure becomes necessary, the company will make an announcement promptly.

Company response

Suspended operations

Suspension of train services between Kumamoto and Shin-Minamata stations on the Kyushu Shinkansen and between Uto and Yatsushiro stations on the Kagoshima Main Line

Scheduled resumption date

Kyushu Shinkansen services are expected to resume from 18 September 2026. The company aims to resume Kagoshima Main Line services around mid-October 2026.

Outlook

Kyushu Shinkansen services are expected to resume from 18 September 2026. The company aims to resume Kagoshima Main Line services around mid-October 2026. The expected resumption dates may change depending on the status of aftershocks and other factors. After services resume, trains will operate at reduced speeds on certain sections of the Kyushu Shinkansen, and some services may be cancelled or have their schedules changed.

Planned follow-up disclosure

If timely disclosure becomes necessary, the company will make an announcement promptly.

Event that occurred
ItemDetails
Event nameImpact of the “Reiwa 8 Kumamoto Earthquake”
Date of occurrence28 July 2026
Subject EntityKyushu Railway Company
Target Locations / ProductsKyushu Shinkansen (Kumamoto Station–Shin-Minamata Station); Kagoshima Main Line (Uto Station–Yatsushiro Station)
CauseThe 2026 Kumamoto Earthquake, which occurred on 28 July 2026
Amount of Impact on Business PerformanceThe amount of damage and the impact on financial results remain under investigation. The amount has not yet been determined.
Impact on Earnings ForecastThe amount of damage and the impact on financial results remain under investigation. If timely disclosure becomes necessary, the company will make an announcement promptly.
Suspended operationsSuspension of train services between Kumamoto and Shin-Minamata stations on the Kyushu Shinkansen and between Uto and Yatsushiro stations on the Kagoshima Main Line
Scheduled resumption dateKyushu Shinkansen services are expected to resume from 18 September 2026. The company aims to resume Kagoshima Main Line services around mid-October 2026.
OutlookKyushu Shinkansen services are expected to resume from 18 September 2026. The company aims to resume Kagoshima Main Line services around mid-October 2026. The expected resumption dates may change depending on the status of aftershocks and other factors. After services resume, trains will operate at reduced speeds on certain sections of the Kyushu Shinkansen, and some services may be cancelled or have their schedules changed.
Planned follow-up disclosureIf timely disclosure becomes necessary, the company will make an announcement promptly.
Items this document does not state (14)
Date recognized / date notice receivedAccounting period in which recognizedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The impact of the “Reiwa 8 Kumamoto Earthquake,” which occurred on 28 July 2026.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Impact of the “2026 Kumamoto Earthquake” (Update on Previously Disclosed Matters) | Kyushu Railway Company (9142) timely disclosure | Komori