- FY2024AchievedAnnual report
「The principal asset completed during the current period was the following warehouse dedicated to functional chemicals. SANKYU INC. Takaishi, Osaka Logistics business Kansai Chemical Center 3,351 May 2023 Total floor area: 7,947 m² Buildings: 8 single-story steel-frame buildings」
The facility planned as a hazardous materials warehouse in the Kansai area was completed as the Kansai Chemical Center in May 2023. - FY2023SoftenedAnnual report
「SANKYU INC. Takaishi, Osaka Logistics business Kansai Chemical Center 3,585 1,943 Internal funds May 2022 May 2023 Total floor area: 7,947 m² Buildings: 8 single-story steel-frame buildings」
The plan for the hazardous materials warehouse in the Kansai area remains in place, but the planned investment increased from ¥3,425 million to ¥3,585 million, and the scheduled completion was pushed back from March 2023 to May 2023. - FY2022First statedAnnual report
「SANKYU INC. Takaishi, Osaka Logistics business Kansai-area hazardous materials warehouse 3,425 – Internal funds May 2022 March 2023 Total floor area: 7,934 m² Buildings: 8 single-story steel-frame buildings」