Establishment of SANKYU PLANT TECHNO’s New Kyushu Office

First written in FY2020-Q2. 1 of 4 entries say "Restated". Latest entry: FY2022.

4entries
4years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseFirst statedFY2020-Q2 – FY2020-Q3SoftenedFY20212019: 120192020: 120202021: 120212022: 12022
Same theme, other companies
Establishment of SANKYU PLANT TECHNO’s New Kyushu OfficeA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2022AchievedAnnual report

    「The principal asset completed during the fiscal year was the following office, developed to establish and consolidate manufacturing bases for piping: 山九プラントテクノ New Kyushu Office 1,152 June 2021 Total floor area: 9,259㎡ Building: three-story steel-frame structure」

    The 山九プラントテクノ New Kyushu Office was completed in June 2021, completing the project.
  2. FY2021SoftenedAnnual report

    「山九プラントテクノ Co., Ltd. Wakamatsu-ku, Kitakyushu, Fukuoka Plant and machinery business 山九プラントテクノ New Office 1,323 872 Internal funds July 2019 June 2021 Total floor area: 9,259㎡ Building: three-story steel-frame structure」

    The planned completion of the New Kyushu Office was postponed from March 2021 to June 2021. The amount already paid was ¥872 million.
  3. FY2020-Q3RestatedAnnual report

    「山九プラントテクノ Co., Ltd. Wakamatsu-ku, Kitakyushu, Fukuoka Plant and machinery business 山九プラントテクノ New Kyushu Office 1,323 - Internal funds July 2019 March 2021 Total floor area: 9,259㎡ Building: three-story steel-frame structure」

    The plan for the 山九プラントテクノ New Kyushu Office was reiterated, with a planned investment of ¥1,323 million, construction scheduled to begin in July 2019 and be completed in March 2021, and a total floor area of 9,259㎡.
  4. FY2020-Q2First statedAnnual report

    「山九プラントテクノ Co., Ltd. Wakamatsu-ku, Kitakyushu, Fukuoka Plant and machinery business 山九プラントテクノ New Kyushu Office 1,323 ― Internal funds July 2019 March 2021 Total floor area: 9,259㎡ Building: three-story steel-frame structure」

    A plan to construct the new Kyushu office of 山九プラントテクノ was newly finalized. The planned investment was ¥1,323 million, with construction scheduled to begin in July 2019 and be completed in March 2021. The building was planned as a three-story steel-frame structure with a total floor area of 9,259㎡.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
Sankyu's next results are scheduled for 2026-10-30. Read the earnings preview
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.