Tokaido Line Shimbashi Station Improvement Works
First written in FY2020-Q2. 1 of 2 entries say "Advanced", first in FY2022. Latest entry: FY2022.
2entries
4years
0from disclosures
How it moved
Same theme, other companies
Tokaido Line Shimbashi Station Improvement WorksA theme 1 companies write about · 0 as a headwind · 1 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2022AdvancedAnnual report
「Tokaido Line Shimbashi Station improvement work 32,938 22,242 Internal funds November 2010 March 2031」
The planned total cost of the Tokaido Line Shimbashi Station improvement work remained ¥32,938 million, while the amount already paid reached ¥22,242 million. - FY2020-Q2First statedAnnual report
「In addition, because the construction area for the “Tokaido Line Shimbashi Station improvement work,” which is intended to improve transportation operations, among other things, has expanded, we have changed the planned total cost from ¥23,228 million to ¥32,938 million.」
For the Tokaido Line Shimbashi Station improvement work, we changed the planned total cost from ¥23,228 million to ¥32,938 million due to the expansion of the construction area.