Komori
Chichibu Railway (9012) · RiskWorsened

Natural disaster risk affecting facilities and equipment concentrated along railway lines

First written in FY2016. 5 of 7 entries say "Restated". Latest entry: FY2023.

7entries
8years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2016 – FY20222016: 120162017: 120172018: 120182019: 020192020: 120202021: 120212022: 120222023: 12023
Same theme, other companies

Chichibu Railway moved to the "Worse" side of this theme in 2023, 4 years after the typical company in this theme (2019).

The whole theme swung hardest in 2026: 3 of 6 companies on the "Worse" side.

0 other companies' latest entry also says "Worsened".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
  1. FY2023WorsenedAnnual report

    「To address the natural disasters that have become more frequent and severe in recent years, we will further strengthen our initiatives in both soft and hard measures.」

    In addition to its existing disclosure of natural disaster risk, the company recognizes that natural disasters have become more frequent and severe in recent years and identifies strengthening its response as a challenge.
  2. FY2022RestatedAnnual report

    「The company's railway network consists of the main line from Hanyu Station to Mitsumineguchi Station and the freight line from Takekawa Station to Mikajiri Station. Because the group's facilities and equipment are also concentrated along the railway lines, they could sustain significant damage from earthquakes and other natural disasters.」

    The company continues to identify the natural disaster risk arising from the concentration of facilities and equipment along railway lines, as well as the potential for service suspensions and delays, lower revenue, and recovery and alternative transportation costs.
  3. FY2021RestatedAnnual report

    「Until the facilities and other assets are restored, the company may incur substantial costs for repairing facilities and equipment and providing alternative transportation, while train services may be suspended or delayed and operating revenue may decline for other reasons.」

    The company continues to identify, in addition to damage from natural disasters, the potential for service suspensions and delays, lower revenue, and recovery and alternative transportation costs resulting from the concentration of facilities and equipment along railway lines.
  4. FY2020RestatedAnnual report

    「Until the facilities and other assets are restored, the company may incur substantial costs for repairing facilities and equipment and providing alternative transportation, while train services may be suspended or delayed and operating revenue may decline for other reasons.」

    For the natural disaster risk arising from the concentration of facilities and equipment along railway lines, the company describes potential impacts extending to service suspensions and delays, lower revenue, and recovery and alternative transportation costs.
  5. FY2018RestatedAnnual report

    「The company's railway network consists of the main line from Hanyu Station to Mitsumineguchi Station and the freight line from Takekawa Station to Kumagaya Freight Terminal Station. Because the group's facilities and equipment are also concentrated along the railway lines, they could sustain significant damage from earthquakes and other natural disasters.」

    The company continues to identify the risk of natural disasters arising from the concentration of facilities and equipment along railway lines.
  6. FY2017RestatedAnnual report

    「The company's railway network consists of the main line from Hanyu Station to Mitsumineguchi Station and the freight line from Takekawa Station to Kumagaya Freight Terminal Station. Because the group's facilities and equipment are also concentrated along the railway lines, they could sustain significant damage from earthquakes and other natural disasters.」

    The company continues to identify the risk of natural disasters, such as earthquakes, arising from the concentration of facilities and equipment along railway lines.
  7. FY2016First statedAnnual report

    「The company's railway network consists of the main line from Hanyu Station to Mitsumineguchi Station and the freight line from Takekawa Station to Kumagaya Freight Terminal Station. Because the group's facilities and equipment are also concentrated along the railway lines, they could sustain significant damage from earthquakes and other natural disasters.」

    The concentration of facilities and equipment along railway lines indicates the potential for damage from earthquakes and other events, service suspensions and delays, and recovery and alternative transportation costs.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Chichibu Railway yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.