Handover Timing Delayed by Apartment Construction Delays
First written in FY2019-Q2. 3 of 6 entries say "Materialised", first in FY2019-Q2. Latest entry: FY2020.
The whole theme swung hardest in 2026: 10 of 22 companies on the "Worse" side.
1 other company's latest entry also says "Advanced".
- FY2020AdvancedAnnual report
「During the current consolidated fiscal year, sales commenced for the two condominiums SUNCLEAR Kamisha and SUNCLEAR Sakuradori Izumi.」
Sales of SUNCLEAR Kamisha, whose handover was pushed into the following fiscal year due to construction delays, commenced, followed by the launch of sales for SUNCLEAR Sakuradori Izumi. - FY2020-Q3Continued sales of delayed property and launch of sales for new propertyAnnual report
「During the nine months ended the third quarter of the current consolidated fiscal year, sales of SUNCLEAR Kamisha, whose construction had been delayed despite its scheduled sale and handover in the previous consolidated fiscal year, commenced in the first quarter. Sales of SUNCLEAR Sakuradori Izumi also commenced in February.」
Sales of SUNCLEAR Kamisha, whose handover was pushed into the following fiscal year due to construction delays, commenced, and sales of the new SUNCLEAR Sakuradori Izumi also began. - FY2020-Q2Start of sales and handovers for delayed propertyAnnual report
「During the six months ended the second quarter of the current consolidated fiscal year, construction of SUNCLEAR Kamisha (27 units), which had been scheduled for sale and handover in the previous consolidated fiscal year, was delayed, and sales commenced in the first quarter of the current consolidated fiscal year.」
Sales of SUNCLEAR Kamisha, whose handover was pushed into the following fiscal year due to construction delays, commenced, and 9 units had been handed over in the six months ended the second quarter. However, the condominium business recorded an operating loss. - FY2019MaterialisedAnnual report
「Because construction was delayed, handover of SUNCLEAR Kamisha (27 units), which had been scheduled for the current consolidated fiscal year, was pushed back to the next fiscal year.」
Handover of all 27 units at SUNCLEAR Kamisha was in fact pushed back to the following fiscal year due to construction delays. - FY2019-Q3MaterialisedAnnual report
「We are also preparing for the sale of SUNCLEAR Kamisha (27 units), which was scheduled for handover from June 2019 through the following consolidated fiscal year. However, partly because construction has been delayed, handover will extend into the following consolidated fiscal year.」
The wording concerning the postponement of handover for SUNCLEAR Kamisha changed from an expectation that it would be delayed to a statement that it will be delayed, confirming that construction delays resulted in the handover being pushed back. - FY2019-Q2MaterialisedAnnual report
「We are preparing for the sale of SUNCLEAR Kamisha (27 units), which was scheduled for handover from June 2019 through the following consolidated fiscal year. However, partly because construction has been delayed, handover is now expected to extend into the following consolidated fiscal year.」
Because construction of SUNCLEAR Kamisha was delayed, handover of all 27 units is expected to extend from the original schedule into the following consolidated fiscal year.