Preparation for Metsä’s opening, basic design and acquisition of development land
First written in FY2016-Q3. 6 of 11 entries say "Advanced", first in FY2017-Q2. Latest entry: FY2019-Q2.
No other company in this theme has enough history to compare yet.
- FY2019-Q2AchievedAnnual report
「During the first half of the current fiscal year, Metsa Village opened on 9 November 2018 and Moominvalley Park on 16 March 2019, enabling the Group to begin recording revenue from admission fees, paid facility-use fees, merchandise, food and beverages, tenant rents and parking fees, among other sources.」
Metsa Village and Moominvalley Park opened, and the project moved from the opening preparation and construction phase to operations and revenue recognition. - FY2019-Q1AdvancedAnnual report
「During the first quarter of the current fiscal year, Metsa, comprising Metsa Village and Moominvalley Park, which began construction in July 2017, was completed in October 2018. Metsa Village opened ahead of schedule on 9 November 2018, and began recording revenue from tenant rents and fees for use of various facilities and services. Metsa Village attendance exceeded 100,000 on 2 December 2018 and remained on track. Moominvalley Park was scheduled to open on 16 March 2019.」
Metsa as a whole was completed in October 2018, and Metsa Village opened on 9 November. Attendance exceeded 100,000 on 2 December, and the project progressed into the operating phase after opening, with rental and facility-use revenue being recorded. Moominvalley Park was scheduled to open on 16 March 2019. - FY2018-Q3AdvancedAnnual report
「For Metsa Village, tenant agreements, including with Nordic companies, progressed with the opening date set for 9 November 2018. For Moominvalley Park, the grand opening date was set for 16 March 2019, and preparations such as the design of various content proceeded. Construction of the facilities had reached the topping-out stage, except for certain areas, and finishing work on the interiors and exteriors was under way. Work also progressed on landscaping around the facilities, detailed operating procedures and recruitment of operating staff.」
The opening dates for Metsa Village and Moominvalley Park were set, respectively. Construction had reached the topping-out stage except for certain areas, followed by interior and exterior finishing work, establishment of the operating structure and staff recruitment. - FY2018-Q2AdvancedAnnual report
「Construction began under a contract for the specialised interior and exterior work at Moominvalley Park. For Metsa Village, tenant agreements, including with Nordic companies, progressed with the opening date set for 9 November 2018. Other preparations for opening, including recruitment of opening staff, also proceeded.」
Specialised interior and exterior construction work began at Moominvalley Park, and construction contracts were signed for ¥940 million of movable property and ¥1.12 billion of real property. The opening date for Metsa Village was set for 9 November 2018, and progress was made on tenant agreements and staff recruitment. - FY2018-Q1AdvancedAnnual report
「Construction of Metsa progressed as infrastructure trunk lines and civil engineering work advanced into foundation work, in line with the plan. We agreed with the local government, the City of Hanno, that Hanno would contribute ¥150 million toward the cost of facilities required to open Metsa Village in December 2017 and signed a memorandum of understanding. In addition, Hanno Regional Resources Utilisation GK, a subsidiary and special-purpose company holding the real estate for Moominvalley Park, entered into a silent partnership agreement with Hanno under which Hanno contributed ¥50 million toward construction and development.」
Metsa construction progressed from infrastructure and civil engineering work to foundation work, in line with the plan. A framework was also established to receive a ¥150 million project contribution and a ¥50 million investment from the City of Hanno. - FY2017RestatedAnnual report
「Construction of Metsa began in July 2017, and financing through the real estate securitisation of Moominvalley Park was completed, marking a major milestone in addressing the Metsa project's financing challenge.」
Construction of Metsa had begun, and financing through real estate securitisation had been completed. Preparations for opening continued. - FY2017-Q3AdvancedAnnual report
「The Company obtained development permission from the local government, the City of Hanno, dated 29 May 2017, and on 29 June 2017 entered into a construction contract for Metsa Village civil engineering work with a joint venture comprising 3 local construction companies. Construction of Moominvalley Park was contracted on 29 June 2017 by Hanno Regional Resources Utilisation GK, a special-purpose company that became a subsidiary on 12 July 2017, and construction of both projects began on 3 July 2017.」
Development permission for Metsa was obtained, construction contracts for Metsa Village and Moominvalley Park were executed, and construction began. The project advanced from development preparations to the construction phase. - FY2017-Q2AdvancedAnnual report
「Preparations for Metsa's opening proceeded. The project moved into the detailed design phase for the buildings, infrastructure and other facilities, while construction costs were estimated based on the detailed design and financing discussions proceeded in parallel. The Company also held preliminary discussions with the local government in preparation for its application for development permission and submitted the application on 2 May 2017. The Company expected to receive permission in June 2017.」
The project moved into the detailed design phase, and after advancing construction cost estimates, financing discussions and preliminary discussions with the local government, the Company applied for development permission on 2 May 2017. - FY2017-Q1RestatedAnnual report
「Preparations for Metsa initially proceeded with an opening planned for 2017, but we concluded that a longer construction period and additional preparation time than initially anticipated would be necessary to create facilities that fully embody the Metsa concept, including the construction of infrastructure across the extensive site. Accordingly, at a meeting of the Company's Board of Directors held on 6 December 2016, it resolved that the opening of Metsa Village would change to autumn 2018 and the grand opening of Moominvalley Park would change to spring 2019.」
The change in opening dates to autumn 2018 and spring 2019, respectively, and the reasons for it are again described. - FY2016SoftenedAnnual report
「Metsa, a facility where visitors can experience a Nordic atmosphere and the world of the Moomins, completed its basic design after the formulation and validation of its business concept and basic plan, based on extensive marketing.」
While basic design was completed, the opening dates, initially planned for 2017, were changed to autumn 2018 for Metsa Village and spring 2019 for Moominvalley Park. - FY2016-Q3First statedAnnual report
「During the third quarter, we completed the formulation and validation of the business concept and basic plan and moved into basic design. We plan to announce the opening date during 2016. Payment of the purchase price and handover of the Metsa development land were completed on 31 May 2016 under the sale and purchase agreement dated 30 June 2015.」
The project moved from the business concept and basic plan to basic design, and payment and handover of the development land were completed. The opening date was scheduled to be announced during 2016.