Komori
Occurring Fact8093Kyokuto Boeki Kaisha,LimitedTrading & Wholesale

Notice Regarding the Recognition of an Extraordinary Loss

Because observation equipment for offshore wind power generation failed and was taken offline, making it impossible to obtain observation data, ¥736 million was recorded as an extraordinary loss.

Worth reading
51Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Deterioration
Direction inferred from the company’s description.
Scale
736
Million yen (extraordinary loss: loss related to contracted work)
Wording
Conditional
How definitive the wording is.

Recognition of an extraordinary loss

Subject Entity

Kyokuto Boeki Kaisha,Limited (filing company)

Target Locations / Products

Observation equipment installed for wind and ocean condition monitoring operations related to the offshore wind power generation business

This disclosure11/12/2026
Cause

The installed observation equipment developed a fault and was taken offline. The cause has not been identified and the equipment has not been restored.

Amount of Impact on Business Performance

¥736 million (extraordinary loss: loss related to contracted work)

Accounting period in which recognized

The interim consolidated accounting period of the fiscal year ending March 2027 (1 April 2026 to 30 September 2026)

Impact on Earnings Forecast

For the full-year consolidated earnings forecast for the fiscal year ending March 2027, including the recognition of the above extraordinary loss, see the “Notice Concerning Revisions to Earnings Forecasts” announced today.

Company response

Suspended operations

Operation of observation equipment and collection of observation data for part of the work covered by this matter

Outlook

We will proceed with measures involving the relevant parties, beginning with discussions with the party that commissioned the work covered by this matter. We will also take appropriate action with the supplier. We will promptly disclose any matters requiring disclosure, including the incurrence of additional costs.

Planned follow-up disclosure

If any matters requiring disclosure arise in the future, including the incurrence of additional costs, we will promptly disclose them.

Event that occurred
ItemDetails
Event nameRecognition of an extraordinary loss
Subject EntityKyokuto Boeki Kaisha,Limited (filing company)
Target Locations / ProductsObservation equipment installed for wind and ocean condition monitoring operations related to the offshore wind power generation business
CauseThe installed observation equipment developed a fault and was taken offline. The cause has not been identified and the equipment has not been restored.
Amount of Impact on Business Performance¥736 million (extraordinary loss: loss related to contracted work)
Accounting period in which recognizedThe interim consolidated accounting period of the fiscal year ending March 2027 (1 April 2026 to 30 September 2026)
Impact on Earnings ForecastFor the full-year consolidated earnings forecast for the fiscal year ending March 2027, including the recognition of the above extraordinary loss, see the “Notice Concerning Revisions to Earnings Forecasts” announced today.
Suspended operationsOperation of observation equipment and collection of observation data for part of the work covered by this matter
OutlookWe will proceed with measures involving the relevant parties, beginning with discussions with the party that commissioned the work covered by this matter. We will also take appropriate action with the supplier. We will promptly disclose any matters requiring disclosure, including the incurrence of additional costs.
Planned follow-up disclosureIf any matters requiring disclosure arise in the future, including the incurrence of additional costs, we will promptly disclose them.
Items this document does not state (15)
Date of occurrenceDate recognized / date notice receivedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionScheduled resumption dateInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

The observation equipment that had been installed developed a fault and was taken offline, making it impossible to obtain the observation data required under the contract. We requested restoration and improvements from the supplier and provided technical support, but the cause could not be identified and the equipment could not be restored. We have determined that it is difficult to establish a prospect of fulfilling the work covered by this matter.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Recognition of an Extraordinary Loss | Kyokuto Boeki Kaisha,Limited (8093) timely disclosure | Komori