Komori
Mitani (8066) · InitiativeRestated

Expansion of the Wind and Solar Power Generation Business

First written in FY2016. 22 of 25 entries say "Restated". Latest entry: FY2026.

25entries
11years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseRestatedFY2017-Q2 – FY2023-Q1RestatedFY2023 – FY20262016: 320162017: 320172018: 320182019: 420192020: 320202021: 320212022: 320222023: 220232024: 020242025: 020252026: 12026
Same theme, other companies
Expanding the Solar, Wind and Biomass Power PortfolioA theme 34 companies write about · 0 as a headwind · 41 as a tailwind

The whole theme swung hardest in 2025: 2 of 20 companies on the "Worse" side.

6 other companies' latest entry also says "Restated".

Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Showing 14 of the 34 companies compared. The sentences above are computed from all 34.
Full recordFilings, disclosures and news, newest first
  1. FY2026RestatedAnnual report

    「Specifically, in Japan, the company operates 20 wind power generation units (40,000 kWh) and 1,000 kWh of solar power generation as renewable energy businesses.」

    The company has reiterated the operating status of 20 domestic wind power units with 40,000 kWh of capacity and 1,000 kWh of solar power generation. It does not mention the commissioning of new facilities.
  2. FY2023RestatedAnnual report

    「Specifically, in Japan, the company operates 20 wind power generation units (40,000 kWh) and 1,000 kWh of solar power generation as renewable energy businesses.」

    The sustainability disclosure specifies the number and generation capacity of the existing wind and solar power facilities. It does not mention the commissioning of new facilities.
  3. FY2023-Q3AdvancedAnnual report

    「Profit increased in the wind power business this fiscal year, partly because fewer repairs requiring turbines to be taken offline improved the operating rate.」

    The company describes an operational improvement in which fewer repairs requiring turbines to be taken offline led to a higher operating rate.
  4. FY2023-Q1RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines in Ibaraki Prefecture and 5 onshore wind turbines in Aomori Prefecture, but does not mention the commissioning of any new facilities.
  5. FY2022RestatedAnnual report

    「Our domestic new businesses include 15 offshore wind-power facilities in Ibaraki Prefecture and 5 onshore wind-power facilities in Aomori Prefecture, which are now operating. In January 2018, we also entered the ODA trading business, exporting and selling medical equipment and various industrial materials to developing countries.」

    The company continues to describe the operating and market-entry status of its 15 offshore wind turbines, 5 onshore wind turbines and ODA trading business.
  6. FY2022-Q3RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines and 5 onshore wind turbines, but does not indicate the commissioning of any new power generation facilities or expansion plans.
  7. FY2022-Q2RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines and 5 onshore wind turbines, but does not mention the commissioning of any new power generation facilities.
  8. FY2022-Q1RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines in Ibaraki Prefecture and 5 onshore wind turbines in Aomori Prefecture, but does not mention the commissioning of any new facilities.
  9. FY2021-Q3RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines in Ibaraki Prefecture and 5 onshore wind turbines in Aomori Prefecture, but does not mention the commissioning of any new facilities.
  10. FY2021-Q2RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines in Ibaraki Prefecture and 5 onshore wind turbines in Aomori Prefecture, but does not mention the commissioning of any new facilities.
  11. FY2021-Q1RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines in Ibaraki Prefecture and 5 onshore wind turbines in Aomori Prefecture, but does not mention the commissioning of any new facilities.
  12. FY2020-Q3RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines in Ibaraki Prefecture and 5 onshore wind turbines in Aomori Prefecture, but does not mention the commissioning of any new facilities.
  13. FY2020-Q2RestatedAnnual report

    「In domestic new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines and 5 onshore wind turbines, but does not mention the commissioning of any new power generation facilities.
  14. FY2020-Q1RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company has reiterated the operating status of 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture, but does not mention the commissioning of any new facilities.
  15. FY2019RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company has reiterated the operating status of its existing 15 and 5 wind power facilities and the mega-solar facility in Hyogo Prefecture, but does not mention the commissioning of any new facilities.
  16. FY2019-Q3RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company has reiterated the operating status of its existing facilities, comprising 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture.
  17. FY2019-Q1RestatedAnnual report

    「Operating income and ordinary income increased, owing to strong performance in the wind power and information systems businesses, lower retirement benefit expenses, and the recognition of foreign exchange gains, among other factors.」

    The existing wind power business performed well and contributed to higher profit, but no new power generation facilities or expansion plans are mentioned.
  18. FY2018RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company has reiterated the operating record for 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture, but does not mention the commissioning of any new facilities.
  19. FY2018-Q3RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company continues to describe its existing renewable energy businesses, comprising 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture.
  20. FY2018-Q2RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company continues to describe its existing renewable energy businesses, comprising 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture.
  21. FY2018-Q1RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 onshore wind power facilities are operating in Aomori Prefecture. The company has also entered the solar power business, and a mega-solar facility, or large-scale solar power plant, is currently operating in Hyogo Prefecture.」

    The company has reiterated the operating status of its existing facilities, comprising 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture.
  22. FY2017-Q3RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 new onshore wind power facilities in Aomori Prefecture have been operating since November 2014. The company then entered the solar power business. A mega-solar facility, or large-scale solar power plant, in Hyogo Prefecture has been operating since February 2014.」

    The company has reiterated its operating record for its existing renewable energy businesses, comprising 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture.
  23. FY2017-Q2RestatedAnnual report

    「In new businesses, following 15 offshore wind power facilities in Ibaraki Prefecture, 5 new onshore wind power facilities in Aomori Prefecture have been operating since November 2014. The company then entered the solar power business. A mega-solar facility, or large-scale solar power plant, in Hyogo Prefecture has been operating since February 2014.」

    The company has reiterated its operating record for 15 offshore wind turbines, 5 onshore wind turbines and the mega-solar facility in Hyogo Prefecture, but does not state that any new facilities began operating during the quarter.
  24. FY2017-Q1AdvancedAnnual report

    「Profit from the gondola and wind power businesses increased.」

    The company reported higher profit from the wind power business in the quarter, although this did not result from the commissioning of new facilities.
  25. FY2016First statedAnnual report

    「In new businesses, we have been engaged in renewable energy businesses, including wind power generation, since 2010.」

    Since 2010, the company has been engaged in wind power generation, operating 15 offshore wind turbines in Ibaraki Prefecture, 5 onshore wind turbines in Aomori Prefecture, and a mega-solar facility in Hyogo Prefecture.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Mitani yet.
News