Construction of the Toyomi Distribution and Delivery Center
First written in FY2016. 2 of 4 entries say "Softened", first in FY2020. Latest entry: FY2022.
No other company in this theme has enough history to compare yet.
- FY2022AchievedAnnual report
「The Toyomi Distribution Center began operations in April 2022. By leveraging its location near Toyosu Market, it enables the efficient delivery of seafood and other products, and we aim to further expand the group's performance.」
The start of operations at the Toyomi Distribution Center in April 2022 is stated, marking the transition from the previously scheduled completion stage to actual operations. - FY2021SoftenedAnnual report
「The Toyomi Distribution Center is scheduled for completion in spring 2022. By leveraging its location near Toyosu Market, the center will enable the efficient delivery of seafood and other products, and we aim to further expand the group's performance.」
The scheduled completion was pushed back from autumn 2021 to spring 2022. Meanwhile, the functions of efficient delivery from a site near Toyosu Market and the objective of expanding performance have been maintained. - FY2020SoftenedAnnual report
「The Toyomi Distribution Center is scheduled for completion in autumn 2021. By leveraging its location near Toyosu Market, the center will enable the efficient delivery of seafood and other products, and we aim to expand the group's overall performance.」
The scheduled completion was changed from the previous target of May 2018 to autumn 2021, pushing back the project timeline. The functions of efficient delivery from a site near Toyosu Market and the objective of expanding performance have been maintained. - FY2016First statedAnnual report
「In addition, we plan to construct the Toyomi Distribution and Delivery Center (provisional name) in the Toyomi area of Chuo-ku, near Toyosu Market, with facilities enabling the efficient delivery of seafood and completion targeted for May 2018. To this end, we have formed a cross-group project team and are preparing to establish an operating structure.」
The completion date, delivery functions, cross-group project team and preparations for the operating structure are specified.