654MW Plan for Egypt’s Suez Gulf Wind Farm II
First written in FY2025. 1 of 2 entries say "Achieved", first in FY2026-H1. Latest entry: FY2026-H1.
No other company in this theme has enough history to compare yet.
- FY2026-H1AchievedAnnual report
「In June 2025, Suez Gulf Wind Farm II, which was under construction in Egypt, began commercial operations. With installed capacity of 654MW, the power plant is the largest in Africa, where electricity demand is expected to grow with population increases. Combined with Suez Gulf Wind Farm I, which is already operating, total capacity is 916.5MW.」
The 654MW plan for Suez Gulf Wind Farm II, presented in FY2025, reached commercial operation in June 2025. - FY2025First statedAnnual report
「Also, in November of the same year, we expanded the Suez Gulf Wind Farm II in Egypt, which we are developing with Eurus Energy Holdings Corporation, and revised the plan to increase its capacity to 654MW, making it Africa's largest wind power plant.」
The plan for Egypt’s Suez Gulf Wind Farm II was changed to 654MW through expansion, making it the largest-scale project in Africa, and was described for the first time as an independent initiative.