Plan to expand the buildings at the Kyoto No. 2 Plant
First written in FY2017-Q2. 1 of 3 entries say "Restated". Latest entry: FY2017.
No other company in this theme has enough history to compare yet.
- FY2017AchievedAnnual report
「The above project was completed in April 2017.」
The company states that the Kyoto Second Plant building expansion plan, with planned investment of ¥900 million and completion scheduled for April 2017, was completed. - FY2017-Q3RestatedAnnual report
「At the end of the previous consolidated fiscal year, the Kyoto Second Plant building expansion plan was budgeted at ¥800 million and scheduled for completion in March 2017. During the second quarter of the current consolidated fiscal year, it was changed from ¥900 million to completion in April 2017.」
The revised Kyoto Second Plant building expansion plan is restated as a budget of ¥900 million with completion scheduled for April 2017. - FY2017-Q2First statedAnnual report
「At the end of the previous consolidated fiscal year, the Kyoto Second Plant building expansion plan was budgeted at ¥800 million and scheduled for completion in March 2017. During the second quarter of the current consolidated fiscal year, it was changed from ¥900 million to completion in April 2017.」
The Kyoto Second Plant building expansion plan was changed from ¥800 million to ¥900 million and from completion in March 2017 to April 2017.