Acquisition of Land for the Expansion of Headquarters and Domestic Plant Facilities
First written in FY2020-Q2. 8 of 13 entries say "Advanced", first in FY2023. Latest entry: FY2026-H1.
No other company in this theme has enough history to compare yet.
- FY2026-H1AdvancedAnnual report
「In light of growing market demand for JIZAI, the company has decided to prioritize the product and begin mass production at the Hanaoka Plant in September 2026, in the fiscal year ending August 2027.」
The company has stated that, based on market demand for JIZAI, it has decided on a specific operating plan to begin mass production at the domestic smart factory in September 2026. - FY2025AdvancedAnnual report
「During the consolidated fiscal year, the company made capital expenditures of ¥6,671 million, mainly for the building and production equipment of the Hanaoka Plant (smart factory)…」
Following completion of the Hanaoka Plant in January 2025, the group made capital expenditures of ¥6,671 million, including the building and production equipment, of which ¥5,379 million was invested in Japan. - FY2025-H1AdvancedAnnual report
「Construction of the Hanaoka Plant in Japan began in October 2023 and was completed at the end of January 2025. During the interim consolidated accounting period, the company proceeded with establishing a production structure for ophthalmic knives and the NiTi rotary file JIZAI with a view to beginning mass production in 2026.」
The smart factory has reached completion following the start of construction, and the project has progressed to the stage of building a production system for ophthalmic knives and JIZAI ahead of the start of mass production in 2026. - FY2024AdvancedAnnual report
「In Japan, the company made capital expenditures of ¥6,108 million for new-product development, construction of the smart-factory building, machinery and equipment, and other purposes.」
Domestic capital expenditures, including the smart factory, totaled ¥6,108 million, comprising ¥5,592 million of smart-factory-related investment recorded in consolidated property, plant and equipment and ¥5,775 million already paid. - FY2024-Q3AdvancedAnnual report
「This was an increase of ¥3,723 million in property, plant and equipment, mainly reflecting ¥2,981 million of smart-factory-related investment made during the cumulative third quarter of the fiscal year.」
Following the start of smart-factory construction, ¥2,981 million of related investment was made during the cumulative FY2024-Q3 period and reflected as an increase in property, plant and equipment. - FY2024-Q2AdvancedAnnual report
「This was an increase of ¥3,072 million in property, plant and equipment, mainly reflecting ¥2,827 million of smart-factory-related investment made during the cumulative second quarter of the fiscal year.」
Following the start of smart-factory construction, ¥2,827 million of related investment was made during the cumulative FY2024-Q2 period and reflected as an increase in property, plant and equipment. - FY2024-Q1AdvancedAnnual report
「In Japan, construction of the smart factory began in October 2023. The smart factory now under construction is positioned as the first “pilot plant,” intended to establish mass-production technologies for new products and new production processes and to support subsequent overseas expansion, with the aim of expanding global sales while reducing product costs. In particular, preparations are under way for the mass production of the priority development product, the NiTi rotary file “JIZAI,” and ophthalmic knives used in cataract surgery.」
The start of smart-factory construction in October 2023 has been confirmed, and the project is taking concrete shape as a pilot plant with total investment of ¥10,500 million, including mass-production lines for JIZAI and ophthalmic knives. - FY2023AdvancedAnnual report
「The smart factory now under construction is positioned as the first “pilot plant,” intended to establish mass-production technologies for new products and new production processes and to support subsequent overseas expansion, with the aim of expanding global sales while reducing costs.」
The company has disclosed that preparations for construction of the domestic smart factory have been completed, construction is scheduled to begin in October 2023, the planned investment is ¥9,500 million, and completion is scheduled for January 2025. - FY2021Acquisition amount disclosed in full-year resultsAnnual report
「This was mainly due to an increase in cash and deposits and an increase in land following the acquisition of the site planned for the new head office and R&D center (¥2,740 million), among other factors.」
The land increase, including the ¥2,740 million acquisition cost for the site planned for the new head office and R&D center, has been reflected in the full-year statement of financial position. - FY2021-Q3AchievedAnnual report
「This was mainly due to an increase in land following the acquisition of the site planned for the new head office and R&D center, among other factors.」
The acquisition-related increase in land for the site planned for the new head office and R&D center has been disclosed, indicating that the project has progressed from the previous resolution to acquire the land and planned handover to the implementation stage of the acquisition. - FY2020RestatedAnnual report
「④ Handover timing: Scheduled for sometime in 2021」
The scheduled 2021 handover of the site for the head office and domestic plant expansion remains unchanged. - FY2020-Q3Newly disclosed the scheduled handover periodAnnual report
「④ Handover timing: Scheduled for sometime in 2021」
For the site for the head office and domestic plant expansion, the handover timing after contract execution has been additionally disclosed as scheduled for sometime in 2021. Completion of the land acquisition has not yet been reported. - FY2020-Q2First statedAnnual report
「The head office and domestic plants are primarily engaged in the development and production of new products, while overseas plants are primarily engaged in the production of existing products. As development of new products and production technology has intensified, the current head office plant has become too small, creating a need to secure a larger site. In addition, considering the expected increase in production of new products and the increase in the number and size of production machines resulting from automation research, the company determined that it would be advisable to secure sufficient land and plant space over the medium to long term so that these would not constrain R&D or production and to ensure operational flexibility, and resolved to acquire the site. / (2) Area: 287,056㎡ / Contract date: 30 March 2020」
In preparation for more active new-product development and production technology development and future production expansion, the company resolved to acquire 287,056㎡ of land in Takanesawa Town, Shioya County, Tochigi Prefecture, for the head office and domestic plants, and signed the contract on 30 March 2020.