Notice Concerning the Impact of the 2024 Noto Peninsula Earthquake (Fifth Report)

Some production equipment at the Noto Factory has been restored and production processing has resumed, while the supply structure for major products has recovered to a level equivalent to normal operations. The Company expects to record ¥373 million in extraordinary losses for the fiscal year ending May 2024, including restoration costs and losses on the disposal of inventories. The full-year earnings forecast has been revised separately.

Worth reading
51Recurring
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Mixed performance
Direction inferred from the company’s description.
Scale
373
million yen
Wording
Conditional
How definitive the wording is.

令和6年能登半島地震による影響

Subject Entity

シグマ光機株式会社(提出会社)

Target Locations / Products

当社能登工場(石川県羽咋郡志賀町)

Occurrence2024年1月1日
This disclosure05/23/2024
Cause

令和6年能登半島地震

Amount of Impact on Business Performance

373百万円の特別損失(災害による損失)を計上する見込み。うち121百万円は2024年5月期第3四半期の連結決算及び個別決算で計上済み。

Accounting period in which recognized

2024年5月期の通期連結決算及び通期個別決算

Impact on Earnings Forecast

2024年5月期通期業績予想を修正(本日付の別適時開示で公表)

Company response

Suspended operations

当該工場の比較的被害が軽微であった生産設備における生産加工業務(再開済み)

Scheduled resumption date

比較的被害が軽微であった生産設備は再開済み。大部分の生産設備の復旧対応は2024年5月末を目途に完了する見込み。

Outlook

2024年5月末を目途に大部分の生産設備の復旧対応を完了し、製品の安定供給に取り組む。建物及び建物付属設備の二次修繕は2024年6月以降に実施予定で、工期は半年~8ヵ月程度を見込む。グループ生産会社及び生産協力会社の生産能力を増強し、顧客の要望に沿う生産体制の構築を進める。

Event that occurred
ItemDetails
Event name令和6年能登半島地震による影響
Date of occurrence2024年1月1日
Subject Entityシグマ光機株式会社(提出会社)
Target Locations / Products当社能登工場(石川県羽咋郡志賀町)
Cause令和6年能登半島地震
Amount of Impact on Business Performance373百万円の特別損失(災害による損失)を計上する見込み。うち121百万円は2024年5月期第3四半期の連結決算及び個別決算で計上済み。
Accounting period in which recognized2024年5月期の通期連結決算及び通期個別決算
Impact on Earnings Forecast2024年5月期通期業績予想を修正(本日付の別適時開示で公表)
Suspended operations当該工場の比較的被害が軽微であった生産設備における生産加工業務(再開済み)
Scheduled resumption date比較的被害が軽微であった生産設備は再開済み。大部分の生産設備の復旧対応は2024年5月末を目途に完了する見込み。
Outlook2024年5月末を目途に大部分の生産設備の復旧対応を完了し、製品の安定供給に取り組む。建物及び建物付属設備の二次修繕は2024年6月以降に実施予定で、工期は半年~8ヵ月程度を見込む。グループ生産会社及び生産協力会社の生産能力を増強し、顧客の要望に沿う生産体制の構築を進める。
Items this document does not state (14)
Date recognized / date notice receivedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the changePlanned follow-up disclosure

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

令和6年能登半島地震による能登工場の被害が原因です。供給体制の回復については、当社の各生産拠点、グループ生産会社、サプライヤー、生産協力会社と連携し、一部代替生産を進めたためと説明しています。特別損失は、有形固定資産の復旧費用、棚卸資産の廃棄損、その他の災害関連損失によるものです。

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Concerning the Impact of the 2024 Noto Peninsula Earthquake (Fifth Report) | SIGMA KOKI CO.,LTD. (7713) timely disclosure | Komori