Occurring Fact7713SIGMA KOKI CO.,LTD.Electrical Equipment and Precision Instruments

Notice Concerning the Impact of the 2024 Noto Peninsula Earthquake (Second Report)

The Noto Peninsula Earthquake caused partial damage to the buildings, production equipment, and water and sewage facilities at the Noto Factory. The Technical Center suffered no damage, and the Company plans to resume the assembly and inspection processes at the Noto Factory that sustained relatively little damage on 22 January.

Worth reading
37Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Mixed performance
Direction inferred from the company’s description.
Scale
—
Displayed only when the document provides numerical figures.
Wording
Avoiding a definitive answer
How definitive the wording is.

令和6年能登半島地震による影響

Subject Entity

SIGMA KOKI CO.,LTD.

Target Locations / Products

能登工場(羽咋郡志賀町)、技術センター(白山市)

Occurrence2024年1月1日
This disclosure01/19/2024
Cause

令和6年能登半島地震

Company response

Suspended operations

能登工場の生産業務の一部。被害の少ない組立工程・検査工程は再開を計画している。

Scheduled resumption date

22 January 2024

Impact on Earnings Forecast

今回の地震による当社グループの業績への影響につきましては引き続き調査中であります。業績に重大な影響を及ぼすことが見込まれる場合は速やかにお知らせいたします。

Outlook

被害状況の確認を進め、被害の少ない生産工程から復旧活動に注力し、段階的かつ早期の生産活動再開を目指す。業績に重大な影響を及ぼすことが見込まれる場合は速やかに知らせる。

Planned follow-up disclosure

If a material impact on business performance is expected, the Company will promptly disclose the information.

Event that occurred
ItemDetails
Event name令和6年能登半島地震による影響
Date of occurrence2024年1月1日
Subject EntitySIGMA KOKI CO.,LTD.
Target Locations / Products能登工場(羽咋郡志賀町)、技術センター(白山市)
Cause令和6年能登半島地震
Impact on Earnings Forecast今回の地震による当社グループの業績への影響につきましては引き続き調査中であります。業績に重大な影響を及ぼすことが見込まれる場合は速やかにお知らせいたします。
Suspended operations能登工場の生産業務の一部。被害の少ない組立工程・検査工程は再開を計画している。
Scheduled resumption date22 January 2024
Outlook被害状況の確認を進め、被害の少ない生産工程から復旧活動に注力し、段階的かつ早期の生産活動再開を目指す。業績に重大な影響を及ぼすことが見込まれる場合は速やかに知らせる。
Planned follow-up disclosureIf a material impact on business performance is expected, the Company will promptly disclose the information.
Items this document does not state (15)
Date recognized / date notice receivedAmount of Impact on Business PerformanceAccounting period in which recognizedType of litigation or proceedingCourt or authorityPlaintiffDefendantDate of filing / date of actionClaim amount / surcharge amountAmount of receivables at risk of non-collection or delayed collectionInvestigation structureMeasures to prevent recurrenceDirectors' and officers' liabilityVoting rights ownership percentage before the changeVoting rights ownership percentage after the change

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

令和6年能登半島地震による被害。

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Concerning the Impact of the 2024 Noto Peninsula Earthquake (Second Report) | SIGMA KOKI CO.,LTD. (7713) timely disclosure | Komori