Announced details
Research and development, offices, head office functions
BEI = 0.6 or lower (40% reduction in energy consumption from the baseline value of 1.0)
12-17 Kako-machi, Naka-ku, Hiroshima City, Hiroshima Prefecture (head office location)
In this announcement the company addresses none of Contract Value / Offering price / Impact on Business Performance.
| Item | Details |
|---|---|
| Launch date | February 2027 (construction scheduled to begin), December 2029 (new building scheduled for completion), August 2031 (entire project scheduled for completion) |
| Applicable area | Research and development, offices, head office functions |
| Location | 12-17 Kako-machi, Naka-ku, Hiroshima City, Hiroshima Prefecture (head office location) |
| Location scale | Approximately 8,800 sq. m. (gross floor area), 8 floors. Floors 3–5 will mainly house research and development functions, and floors 6–7 will mainly house head office functions. |
| Quantitative Effects | BEI = 0.6 or lower (40% reduction in energy consumption from the baseline value of 1.0) |
Items this document does not state (13)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The aging of the current head office building and its insufficient earthquake resistance are making it increasingly difficult to continue business operations. The project is also intended to maintain and strengthen research and development activities, promote the functions of the head office and interaction among departments, improve the working environment, conserve and generate energy, and enhance disaster prevention and mitigation measures.