Delay in Launch of Production Site for New Service
First written in FY2018. 1 of 2 entries say "Materialised", first in FY2018. Latest entry: FY2019-Q1.
2entries
1years
0from disclosures
How it moved
Same theme, other companies
Delay in Full-Scale Operations Due to Delays in Equipment Installation and Securing Personnel at the New PlantA theme 5 companies write about · 5 as a headwind · 0 as a tailwind
2 other companies' latest entry also says "Mitigated".
Ridges = years it wrote progress, valleys = years it wrote worse. Most hopeful companies at the back. Drag to turn, scroll to zoom, right-drag to pan. On a phone, two fingers turn and pinch to zoom; one finger scrolls the page.
Full recordFilings, disclosures and news, newest first
- FY2019-Q1MitigatedAnnual report
「The Company's newly built large-scale factory, established to fully launch the online business, began operations」
The company reported that, following the delay in launching the production site for new services described in the previous fiscal year, the plant had progressed to the start of operations. - FY2018MaterialisedAnnual report
「Expenses arising from delays in launching a plant that would serve as a production site for new services in the printing business, as well as from the reorganization of the group carried out during the third quarter」
The actual delay in launching the plant intended as a production site for new services was reported as a factor affecting the performance of the printing business.