Muraki (7477) · RiskMitigated
Delayed progress on the new initiative of the Muraki Project
First written in FY2016. 1 of 3 entries say "Materialised", first in FY2016. Latest entry: FY2017.
3entries
2years
0from disclosures
How it moved
Same theme, other companies
Delays in New Initiatives and Digital RolloutsA theme 1 companies write about · 1 as a headwind · 0 as a tailwind
No other company in this theme has enough history to compare yet.
Full recordFilings, disclosures and news, newest first
- FY2017MitigatedAnnual report
「Progress on MSP-Digital, the fourth phase of the MURAKI Project for the current period, is proceeding as planned,」
The description has changed from the postponement of the MSP-Digital rollout reported in the previous period to an explanation that progress is proceeding as planned in the current period. - FY2017-Q1SoftenedAnnual report
「The rollout of MSP-Digital, the fourth phase of the MURAKI Project, is expected to」
Following the previously reported postponement of the rollout, the wording this quarter indicates that the rollout of MSP-Digital is expected. However, completion of the rollout is not explicitly stated. - FY2016MaterialisedAnnual report
「Following the M-WING-related products launched in the previous year, progress on the Waiting Room initiative, a new project under the MURAKI Project for the current period, was unsatisfactory. The decision to postpone the rollout of MSP-Digital, the fourth phase of the MURAKI Project, until the next fiscal year or later is also considered one of the factors.」
It identifies sluggish progress on the Waiting Room initiative and the postponement of the MSP-Digital rollout as factors behind the failure to meet the performance targets for the period.