Okinawa Financial Group (7350) · InitiativeCompletion delayed and payments increased

Plan to Construct and Relocate the Chatan Branch

First written in FY2024-Q1. 1 of 4 entries say "Restated". Latest entry: FY2025.

4entries
3years
0from disclosures
Share on X
How it moved
ProgressHeldSoftenedWorseOtherFY2024-Q1 – FY20252023: 220232024: 120242025: 12025
Same theme, other companies
Relocation of the Kitatan Branch to a newly built facilityA theme 1 companies write about · 0 as a headwind · 1 as a tailwind

No other company in this theme has enough history to compare yet.

Full recordFilings, disclosures and news, newest first
  1. FY2025Completion delayed and payments increasedAnnual report

    「The Bank of Okinawa, Ltd. Chatan Branch Chatan, Okinawa New construction (relocation) Banking Branch and other facilities 1,104 307 Internal funds June 2023 July 2025」

    The planned investment for the Chatan Branch new construction and relocation plan was ¥1,104 million, with ¥307 million paid to date. The scheduled completion date changed from April 2025 to July 2025.
  2. FY2024-Q3Increase in planned investmentAnnual report

    「The Bank of Okinawa, Ltd. Chatan Branch Chatan, Okinawa New construction (relocation) Banking Branch interior Office equipment 1,104 2 Internal funds June 2023 April 2025」

    The total planned investment for the Chatan Branch new construction and relocation plan increased from ¥824 million through the previous quarter to ¥1.104 billion. The ¥2 million paid to date, funding from internal funds and completion scheduled for April 2025 remained unchanged.
  3. FY2024-Q2RestatedAnnual report

    「The Bank of Okinawa, Ltd. Chatan Branch Chatan, Okinawa New construction (relocation) Banking Branch interior Office equipment 824 2 Internal funds June 2023 April 2025」

    The Company continued to disclose the Chatan Branch new construction and relocation plan, with a total investment of ¥824 million, ¥2 million paid to date, funding from internal funds and completion scheduled for April 2025.
  4. FY2024-Q1First statedAnnual report

    「The Bank of Okinawa, Ltd. Chatan Branch Chatan, Okinawa New construction (relocation) Banking Branch interior and office equipment 824 - Internal funds June 2023 April 2025」

    The Company newly finalised a new construction and relocation plan for the Chatan Branch, including branch interior work and office equipment. The total planned investment is ¥824 million, with work commencing in June 2023 and completion scheduled for April 2025, funded with internal funds.
Moved together

None of this company's other threads moved the same way in the same document twice or more.

When this could move next
No upcoming earnings preview for Okinawa Financial Group yet.
News
No news is linked to this thread yet. When an article touches it, it will appear here by date.
Plan to Construct and Relocate the Chatan Branch | Okinawa Financial Group,Inc. (7350) | Komori