Announced details
Automotive parts production
255 Oaza Tajiri, Nakatsu, Oita Prefecture
The company states that the project will contribute to sustainable growth, but no specific amount of impact on results is provided
The company does not address Contract Value / Offering price.
| Item | Details |
|---|---|
| Names of Products / Services Covered | Automotive parts (including automotive suspension components) |
| Contract Date | 18 September 2026 (stated as the investment decision date) |
| Launch date | October 2028 (planned start of operations) |
| Applicable area | Automotive parts production |
| Location | 255 Oaza Tajiri, Nakatsu, Oita Prefecture |
| Location scale | New building with approximately 3,000 m² of floor space and a 2,000-ton press machine |
| Impact on Business Performance | The company states that the project will contribute to sustainable growth, but no specific amount of impact on results is provided |
Items this document does not state (11)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.High production loads have continued in the Kyushu region, and further growth in production demand is expected. The company aims to establish a production system capable of meeting current demand and accommodating future order growth.