Notice Regarding the Execution of a Fixed-Term Building Lease Agreement for the Next-Generation AI Data Center Project (Saku City, Nagano Prefecture)

A subsidiary of the company entered into a 20-year fixed-term building lease agreement covering a factory building and site in Saku City, Nagano Prefecture, securing a site for an edge AI data center. The company will next proceed with preparations to install equipment and conduct a proof-of-concept (PoC) test.

Worth reading
28Immaterial
0–100. This measures how worthwhile something is to read, not how good or bad the company is.
Direction
Neutral
Direction inferred from the company’s description.
Scale
20
Years (fixed-term building lease period)
Wording
Conditional
How definitive the wording is.

Items stated in the management plan

Edge AI Data Center Construction Project
Publication date 20 October 2026
Key initiatives
01Technology and equipment verification
02Establish an operations and maintenance framework
03Detailed review of profitability
Plan assumptionsBring in 2 MW of high-voltage power, Lease and use an idle factory building owned by an external party and construct the facility in a short period at low cost
Non-financial targetsIndicator name Monitoring, operations and maintenance framework / Target value 24 hours a day, 365 days a year / Timing When the PoC is conducted
Items stated in the management plan
ItemDetails
Plan nameEdge AI Data Center Construction Project
Non-financial targetsIndicator name Monitoring, operations and maintenance framework / Target value 24 hours a day, 365 days a year / Timing When the PoC is conducted
Plan assumptionsBring in 2 MW of high-voltage power, Lease and use an idle factory building owned by an external party and construct the facility in a short period at low cost
Key initiativesTechnology and equipment verification, Establish an operations and maintenance framework, Detailed review of profitability
Publication date20 October 2026
Items this document does not state (20)
Plan periodProgress against the planSales TargetOperating profit targetOperating profit margin targetNet income targetROE targetROIC targetPayout ratio / DOE policyTreasury share acquisition policyCost of capitalSelf-assessment of PBR and share priceTotal investment planInvestment amount by sectorSegment targetResults under the previous planReason for revision or withdrawalSize of the Target MarketRisks identifiedDate of board resolution

These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.

The reasons the company gives

The company's own explanation, not something inferred from the numbers.

To consider entering the digital infrastructure sector as part of efforts to develop new businesses and promote alliances.

How to read this page

This is not the documentKomori reads the disclosure the company filed and writes this summary. Figures are as stated by the company and are not audited.
Weight is not a verdictIt measures how much this changes what the company had already told the market. It is not a view on the shares.
Corrections happenIf the company reissues this disclosure, the page is rebuilt from the corrected version and the revision number moves up.
Notice Regarding the Execution of a Fixed-Term Building Lease Agreement for the Next-Generation AI Data Center Project (Saku City, Nagano Prefecture) | IKUYO CO.,LTD. (7273) timely disclosure | Komori