Items stated in the management plan
Formulated| Item | Details |
|---|---|
| Plan name | Plan to Relocate the Head Office and Atsugi Plant |
| Progress against the plan | Formulated |
| Key initiatives | Relocation to the New Plant, Facility Integration and Reorganisation, Improved Energy Efficiency, Reduction of Process Losses, Workload reduction, Demolition of the Existing Plant and Clearance of the Site |
| Date of board resolution | 30 September 2026 |
| Publication date | 30 September 2026 |
Items this document does not state (20)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.To improve the efficiency of the production structure at the existing Atsugi Plant and integrate and reorganise the facilities. With the new plant coming online and the introduction of the latest equipment, we expect to improve energy efficiency, reduce process losses and man-hours, and improve production and earnings.