Strengthening supply capacity through construction of second buildings at the Komono and Vietnam plants
First written in FY2016. 2 of 4 entries say "Advanced", first in FY2018-Q1. Latest entry: FY2018.
No other company in this theme has enough history to compare yet.
- FY2018AchievedAnnual report
「December 2016: a second building was added at ムロ テック ベトナム コーポレーション. March 2017: a second building was added at the Komono plant.」
The previously planned additions of second buildings at the Vietnam and Komono plants have been completed as historical milestones. - FY2018-Q3AdvancedAnnual report
「During the cumulative third quarter of the current consolidated fiscal year, the following major facilities planned as of the end of the previous consolidated fiscal year were completed.」
In addition to the buildings and other facilities at the Komono plant that had been planned, with total investment of ¥775.164 million and completion in April 2017, machinery at the Kiyohara head office plant, costing ¥194.130 million and completed in October 2017, and machinery at the Komono plant, costing ¥160.328 million and completed in December 2017, were completed. The filing does not state that the entire plan, including the second building at the Vietnam plant, was completed. - FY2018-Q1AdvancedAnnual report
「During the cumulative first quarter of the current consolidated fiscal year, the following major facilities planned as of the end of the previous consolidated fiscal year were completed: Komono plant, buildings and other facilities, total investment of ¥775.164 million, completed in April 2017.」
The construction of buildings and other facilities related to the planned second building at the Komono plant was completed in April 2017. Since this filing does not state that the second building at the Vietnam plant was completed, this was assessed as partial progress rather than completion of the overall plan. - FY2016First statedAnnual report
「The company plans to construct a second building at the Komono plant in Mie Prefecture, near important customers with significant sales growth, to strengthen supply capacity and improve logistics efficiency, and to construct a second building at the Vietnam plant to strengthen supply capacity for the Asian region.」
The capital investment plan states that the second building at the Komono plant was scheduled for completion in March 2018, and the buildings and other facilities at the Vietnam plant were scheduled for completion in December 2016.