Risk of business suspension due to disasters and other events
First written in FY2018. 3 of 7 entries say "Restated". Latest entry: FY2025-H1.
The whole theme swung hardest in 2020: 69 of 112 companies on the "Worse" side.
- FY2025-H1RestatedAnnual report
「Although the effects of the 2024 Noto Peninsula Earthquake remain in the Hokuriku region, which is the foundation of the Group's business, the economy is gradually recovering, supported by reconstruction and recovery demand and the effects of the Hokuriku Shinkansen extension to Tsuruga.」
Although the effects of the Noto Peninsula Earthquake remain, the Hokuriku economy is gradually recovering, supported by reconstruction and recovery demand. The continuing impact of the disaster was reconfirmed. - FY2024MaterialisedAnnual report
「Meanwhile, in the Hokuriku region, which is the foundation of our business, the 2024 Noto Peninsula Earthquake that occurred in January caused significant damage to some business partners and dealt a major blow to economic activity in the region. We extend our deepest sympathies to everyone affected and will work to help the region recover as quickly as possible.」
The 2024 Noto Peninsula Earthquake damaged business partners and business locations, resulting in an actual impact from the disaster on operations and the regional economy. An increase in property-related expenses, including repairs to damaged branches, was also recorded. - FY2024-Q3MaterialisedAnnual report
「The 2024 Noto Peninsula Earthquake, which occurred on 1 January 2024, damaged the Group's business locations and borrowers, among others. However, the impact of the earthquake on the Group's financial position, operating results and cash flows for the current consolidated fiscal year is expected to be minor.」
The 2024 Noto Peninsula Earthquake damaged business locations and borrowers, among others, and the risk of an actual impact on operations and financial performance from the disaster was recorded. At the same time, the impact on the current consolidated fiscal year is expected to be minor. - FY2022RestatedAnnual report
「The Group has prepared contingency plans based on various emergency scenarios. Depending on the extent of the damage, however, the Group's operations may be temporarily suspended, potentially adversely affecting its business operations, operating results and financial position.」
The response to disaster risks, including earthquakes, typhoons, floods and snow damage, through contingency plans remains. - FY2021RestatedAnnual report
「The Group has prepared contingency plans based on various emergency scenarios. Depending on the extent of the damage, however, the Group's operations may be temporarily suspended, potentially adversely affecting its business operations, operating results and financial position.」
The policy of maintaining contingency plans in response to disaster risks, including earthquakes, typhoons, floods and snow damage, remains. - FY2019MitigatedAnnual report
「The Group has prepared contingency plans based on various emergency scenarios. Depending on the extent of the damage, however, the Group's operations may be temporarily suspended, potentially adversely affecting its business operations, operating results and financial position.」
The preparation of contingency plans based on various emergency scenarios was expressly stated as a response to disaster and other risks. - FY2018First statedAnnual report
「The Group has facilities, including branches and administrative centers, mainly in Toyama Prefecture, but these facilities may at any time be damaged by disasters such as earthquakes and typhoons, or by criminal activity.」
Describes the possibility that branches, administrative centers and other facilities may be damaged by disasters such as earthquakes and typhoons or by criminal activity, resulting in a temporary suspension of operations.