Execution of Solar Power Project Construction, Commencement of Electricity Sales and Project Sales
First written in FY2016. 17 of 25 entries say "Advanced", first in FY2017-Q1. Latest entry: 2026-07-31.
1 other company's latest entry also says "Advanced".
- FY2026AdvancedAnnual report
「In December 2025, we acquired 2 low-voltage solar power plants, increasing the generation capacity of the solar power plants held by our Group by 0.1 MW to 13.1 MW.」
We acquired 2 low-voltage solar power plants, increasing our generation capacity from 13.0 MW to 13.1 MW. - FY2026-H1ReframedAnnual report
「There are currently no projects under development.」
Although there are no new self-developed solar power projects, the O&M business has expanded to 20 sites totaling 31.6 MW, and the corporate PPA track record comprises 2 local government sites and 6 private-sector sites. The focus has shifted from project development toward operations management and PPAs. - FY2025AdvancedAnnual report
「The approximately 8.1 MW solar power plant in Kikuchi, Kumamoto Prefecture, was held through the Kyushu Renewable Energy Investment Limited Partnership (LPS), and our Group held a 50.04% interest. Following the expiration of the partnership agreement, our Group acquired the interest held by the partnership and, as of 22 January 2025, came to hold a 100% interest in the power plant.」
Following completion and the start of operations at the approximately 2.1 MW Otawara project, we came to hold a 100% interest in the approximately 8.1 MW Kikuchi power plant. - FY2025-H1AdvancedAnnual report
「An approximately 2.1 MW solar power plant in Otawara, Tochigi Prefecture, was completed and began operations at the end of April 2024, bringing the total capacity of completed projects in which this business has been involved to 33.5 MW.」
The approximately 2.1 MW Otawara project was completed and began operations at the end of April 2024, bringing the total capacity of completed projects in which we have been involved to 33.5 MW. - FY2024AdvancedAnnual report
「Self-developed project: ① Otawara, Tochigi Prefecture Output capacity: approximately 2.1 MW Completed in April 2024」
The approximately 2.1 MW solar power plant in Otawara, Tochigi Prefecture, which had been under construction, was completed in April 2024. Maintenance and operational management are scheduled to be provided after operations begin. - FY2022-Q3RestatedAnnual report
「The completed projects in which this business has been involved total 31.4 MW. As shown in ① below, 1 site totaling 2.1 MW is scheduled to begin construction. Self-developed projects (under construction): ① Otawara, Tochigi Prefecture Output capacity: approximately 2.1 MW Scheduled for completion in May 2024」
We continue to disclose a portfolio comprising 31.4 MW of completed projects and the approximately 2.1 MW Otawara, Tochigi Prefecture project, scheduled for completion in May 2024. There were no new operations commencements or portfolio changes during the quarter. - FY2022-Q2RestatedAnnual report
「The completed projects in which this business has been involved total 31.4 MW. As shown in ① below, 1 site totaling 2.1 MW is scheduled to begin construction.」
We continue to disclose a portfolio comprising 31.4 MW of completed projects and the 2.1 MW Otawara, Tochigi Prefecture project, which is scheduled to begin construction. There were no new operations commencements or portfolio changes during the quarter. - FY2022-Q1RestatedAnnual report
「The completed projects in which this business has been involved total 31.4 MW. As shown in ① below, 1 site totaling 2.1 MW is scheduled to begin construction.」
We continue to disclose a project portfolio comprising 31.4 MW of completed projects and the 2.1 MW Otawara, Tochigi Prefecture project, which is scheduled to begin construction. There were no new projects commencing operations or portfolio changes during the quarter. - FY2021-Q2AdvancedAnnual report
「The completed projects in which this business has been involved total 31.4 MW. As shown in ① below, 1 site totaling 2.1 MW is scheduled to begin construction.」
Completed projects totaled 31.4 MW, and the approximately 2.1 MW project in Otawara, Tochigi Prefecture, scheduled to begin construction, was expected to be completed in May 2024. - FY2021-Q1AdvancedAnnual report
「Self-developed projects (under construction): ① Otawara, Tochigi Prefecture Output capacity: approximately 2.1 MW Scheduled for completion in May 2024」
An approximately 2.1 MW self-developed project in Otawara, Tochigi Prefecture, is under construction and is scheduled for completion in May 2024. - FY2020-Q3AdvancedAnnual report
「Operations were initially expected to begin in March 2018, but following a change in the schedule, they began at the end of November 2019. ASTRA has provided management and operational services since operations began.」
The approximately 2.2 MW Kirishima, Kagoshima Prefecture project began operations at the end of November 2019 following delays from the original schedule, and moved into the management and operations phase. - FY2020-Q2AdvancedAnnual report
「The completed projects in which this business has been involved now comprise 15 sites totaling 28.9 MW, while projects under construction and projects scheduled to begin construction comprise 3 sites totaling 4.7 MW.」
Completed projects totaled 15 sites and 28.9 MW, while projects under construction or scheduled to begin construction also expanded to 3 sites and 4.7 MW. We also transferred approximately 3.0 MW of existing facilities. - FY2020-Q1AdvancedAnnual report
「As described in item 2 below, we acquired a solar power plant that was already selling electricity. As a result, the completed projects in which this business has been involved totaled 15 sites with a combined capacity of 28.9 MW, while projects under construction totaled 2 sites with a combined capacity of 2.5 MW.」
In the secondary market, we acquired an approximately 0.9 MW operating facility in Yoshimi, Saitama Prefecture, in May 2019. As a result, the cumulative capacity of completed projects expanded to 28.9 MW. - FY2019AdvancedAnnual report
「3. Okayama, Okayama Prefecture Output capacity: approximately 1.2 MW Acquired the facility in March 2019. … (Secondary market) 4. Tochigi, Tochigi Prefecture Output capacity: approximately 2.0 MW Acquired an existing facility in December 2018. 5. Oshu, Iwate Prefecture Output capacity: approximately 0.9 MW Acquired an existing facility in December 2018. … Added approximately 0.1 MW to the existing Sano project in Tochigi and began operations in November 2018. Added approximately 0.3 MW to the existing Kikuchi project in Kumamoto and began operations in November 2018.」
We acquired a newly built facility in Okayama, existing facilities in Tochigi and Oshu, and expanded and commenced operations at the existing Sano and Kikuchi projects. Meanwhile, the planned start of operations for the Kirishima project was postponed to October 2019 or later. - FY2019-Q3AdvancedAnnual report
「(Secondary market) 3. Tochigi, Tochigi Prefecture Output capacity: approximately 2.0 MW Acquired an existing facility in December 2018. 4. Oshu, Iwate Prefecture Output capacity: approximately 0.9 MW Acquired an existing facility in December 2018. (Productivity improvement) 5. Expansion of existing projects Added approximately 0.1 MW to the existing Sano project in Tochigi and began operations in November 2018. Added approximately 0.3 MW to the existing Kikuchi project in Kumamoto and began operations in November 2018.」
In the secondary market, we acquired existing facilities of approximately 2.0 MW in Tochigi and approximately 0.9 MW in Oshu. We also expanded the existing Sano and Kikuchi projects as planned, with operations beginning at both in November 2018. - FY2019-Q2AdvancedAnnual report
「Following completion of the solar power generation facilities as a whole, we entered into a transfer agreement dated 16 October. ASTRA is expected to continue providing inspection, maintenance and other management services for the generation facilities after their transfer. At the time of the disclosure dated 16 October 2018, delivery of the property was scheduled for 22 October 2018, but was postponed to November 2018 because additional work was required for delivery.」
The approximately 2.3 MW Nakatsu, Oita Prefecture project was completed and progressed to the execution of a transfer agreement, while delivery of the property was postponed from the scheduled date of 22 October to November because of additional work. - FY2019-Q1SoftenedAnnual report
「Operations at this project, in which we invested in a silent partnership with a limited liability company on 27 October 2017, were initially expected to begin in April 2018. However, the schedule was changed because of weather and the time required for site preparation work, and operations are now scheduled to begin in August or September 2018. After operations begin, ASTRA will provide management and operational services.」
The planned start of operations for the approximately 2.3 MW project in Nakatsu, Oita Prefecture, was delayed from April 2018 to August or September 2018. - FY2018-Q2SoftenedAnnual report
「Operations were initially expected to begin in March 2018, but the schedule was changed because site preparation work took longer than expected, and operations are now expected to begin in 2019 or later. After operations begin, ASTRA will provide management and operational services.」
The planned start of operations for the approximately 2.2 MW project in Kirishima, Kagoshima Prefecture, was delayed from March 2018 to 2019 or later because of delays in site preparation work. - FY2017-Q3AdvancedAnnual report
「Kirishima, Kagoshima Prefecture Output capacity: approximately 2.2 MW As reported in the securities report for the fiscal year ended March 2016, procedures relating to land development had been delayed, but were completed in October 2016, allowing construction to begin. To limit the business risks to our Group, we are using an investment scheme involving a special-purpose company (SPC) and a silent partnership agreement (an agreement under which ASTRA is the investor and the SPC is the operator). On 16 December 2016, we invested in a limited liability company established to install the solar power generation facilities. Operations are expected to begin in March 2018, after which ASTRA will provide operations management and maintenance services.」
The approximately 2.2 MW Kirishima project completed its land development procedures and proceeded to the investment and construction stages in December 2016. Operations are expected to begin in March 2018. - FY2017-Q1AdvancedAnnual report
「In addition, following the expected further expansion of the business scale resulting from the operation of the above-mentioned solar power plant in Kikuchi, Kumamoto Prefecture, we reviewed the usage of our machinery and equipment. As the machinery and equipment held by our Group are expected to operate and generate electricity steadily each period, we determined that the straight-line depreciation method would more appropriately reflect their actual usage. Accordingly, from the first quarter of the current consolidated fiscal year, we changed the depreciation method for solar power generation facilities (machinery and equipment) from the declining-balance method to the straight-line method.」
For the Kikuchi, Kumamoto Prefecture project, delivery and commencement of operations were completed on 11 July 2016. The depreciation method was also changed to the straight-line method on the assumption that the generation facilities would continue operating. - FY2016First statedAnnual report
「Sano, Tochigi Prefecture Output capacity: approximately 1.1 MW Construction of the solar power generation facilities was delayed compared with the original plan, but was completed on 28 October 2015, and electricity sales began the following day.」
The update covers progress on each project, including completion of and the start of electricity sales from the Sano project, completion of sales of all 13 lots in the Ishioka project, and the start of construction on the approximately 7.8 MW project in Kikuchi, Kumamoto Prefecture.