Sales for this month
October 2026Fiscal year ending March 2027The company disclosed the October power generation status of the solar power plants owned by its group for the fiscal year ending March 2027.
Suspension of power generation at Ishioka Solar Park East due to a malfunction of the power-generation equipment
Restoration of Ishioka Solar Park East is scheduled for completion in November 2026. If the insurer determines that the failure resulted from an accident, the company plans to file an insurance claim for business interruption compensation covering the period during which power generation was suspended.
Month April 2025 / Power Generation 1,205,564 kWh, Month May 2025 / Power Generation 1,210,761 kWh, Month June 2025 / Power Generation 1,296,791 kWh, Month July 2025 / Power Generation 1,787,709 kWh, Month August 2025 / Power Generation 1,518,784 kWh, Month September 2025 / Power Generation 1,248,322 kWh, Month October 2025 / Power Generation 1,126,573 kWh
Scope of aggregation: Solar power plants owned by the Group
| Item | Details |
|---|---|
| Month Covered | October 2026 |
| Fiscal Year Covered | Fiscal year ending March 2027 |
| Scope of aggregation | Solar power plants owned by the Group |
| Year-on-year change in monthly net sales | 99.2 |
| Cumulative Sales from Start of Period | 8,692,443 kWh |
| Cumulative Year-on-Year Change from Start of Period | 92.5 |
| Key KPIs | Indicator name Power Generation / Value 1,117,336 kWh / Year on year 99.2 kWh, Indicator name CO2 reduction effect / Value 614,535 kg-CO2 / Year on year 99.2 kg-CO2 |
| Monthly Commentary | The company disclosed the October power generation status of the solar power plants owned by its group for the fiscal year ending March 2027. |
| Factors Affecting the Change | Suspension of power generation at Ishioka Solar Park East due to a malfunction of the power-generation equipment |
| Measures from the following month onward | Restoration of Ishioka Solar Park East is scheduled for completion in November 2026. If the insurer determines that the failure resulted from an accident, the company plans to file an insurance claim for business interruption compensation covering the period during which power generation was suspended. |
| Monthly trend for the same period last year | Month April 2025 / Power Generation 1,205,564 kWh, Month May 2025 / Power Generation 1,210,761 kWh, Month June 2025 / Power Generation 1,296,791 kWh, Month July 2025 / Power Generation 1,787,709 kWh, Month August 2025 / Power Generation 1,518,784 kWh, Month September 2025 / Power Generation 1,248,322 kWh, Month October 2025 / Power Generation 1,126,573 kWh |
Items this document does not state (11)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The power generation equipment at Ishioka Solar Park East failed on 13 August 2026, and power generation has been suspended. Restoration is scheduled for completion in November 2026. The company has not provided a separate explanation for October's total power generation being below the same month of the previous year.