Sales for this month
August 2026Fiscal year ending March 2027The Company disclosed power generation for August of the fiscal year ending March 2027. Ishioka Solar Park East has suspended power generation due to a failure of its power-generation equipment.
Suspension of power generation at Ishioka Solar Park East due to a failure of its power-generation equipment, Localized thunderstorms around the time of the failure (identified as a possible cause)
Completion of restoration at Ishioka Solar Park East is scheduled for November 2026. If the insurer determines that the failure was caused by an accident, the Company plans to claim business interruption insurance proceeds.
Month Covered August 2025 / Power Generation 1,518,784 kWh
Scope of aggregation: Solar power plants owned by the Group
| Item | Details |
|---|---|
| Month Covered | August 2026 |
| Fiscal Year Covered | Fiscal year ending March 2027 |
| Scope of aggregation | Solar power plants owned by the Group |
| Cumulative Sales from Start of Period | 6,535,115 kWh |
| Sales by category | Hachinohe Hachitaroyama Solar Park 158,547 kWh, Akuto Solar Park 130,192 kWh, Kumamoton Solar Project 1,045,104 kWh, Ishioka Solar Park East 14,028 kWh, Otawara City Kamehisa Solar Power Plant 244,050 kWh, Other owned power plants 10,849 kWh, Total 1,602,770 kWh |
| Key KPIs | Indicator name Panel capacity / Value 13.1 MW / Year on year Not disclosed, Indicator name CO2 reduction effect / Value 881,524 kg-CO2 / Year on year Not disclosed |
| Monthly Commentary | The Company disclosed power generation for August of the fiscal year ending March 2027. Ishioka Solar Park East has suspended power generation due to a failure of its power-generation equipment. |
| Factors Affecting the Change | Suspension of power generation at Ishioka Solar Park East due to a failure of its power-generation equipment, Localized thunderstorms around the time of the failure (identified as a possible cause) |
| Measures from the following month onward | Completion of restoration at Ishioka Solar Park East is scheduled for November 2026. If the insurer determines that the failure was caused by an accident, the Company plans to claim business interruption insurance proceeds. |
| Monthly trend for the same period last year | Month Covered August 2025 / Power Generation 1,518,784 kWh |
Items this document does not state (12)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.At Ishioka Solar Park East, a failure of the power-generation equipment was confirmed on 13 August 2026. Localized thunderstorms occurred around the time of the failure, and may have caused it, but the causal relationship is still under investigation.