Agreements reached under this partnership
Business Alliances- 1
For each project, the parties will be responsible for selecting and introducing developers that wish to install, acquire and operate the facilities, and for procuring and securing battery system components.
- 2
The scope includes rights relating to land attached to the relevant facilities at special high-voltage battery plants, rights relating to grid interconnection, battery systems, aggregator agreements and other matters.
- 3
In particular, with respect to battery systems, the Company plans to deliver them directly to developers and provide support.
These are items that the documents state the two companies will work on. The lines above and below represent arrangements between the two companies.
The Company expects this business alliance to have a minor impact on its results for the current fiscal year (the fiscal year ending June 2027).
| Item | Details |
|---|---|
| Name of alliance partner | 諾亜建設株式会社 |
| Alliance partner's business activities | Development, manufacture and sale of products, systems and services related to energy businesses, including power generation, grid-scale battery storage, hydrogen and decarbonization businesses |
| Alliance partner's location | Nakano-ku, Tokyo |
| Alliance partner's capital | ¥99 million |
| Type of alliance | Business Alliances |
| Details of the alliance | For each project, the parties will be responsible for selecting and introducing developers that wish to install, acquire and operate the facilities, and for procuring and securing battery system components., The scope includes rights relating to land attached to the relevant facilities at special high-voltage battery plants, rights relating to grid interconnection, battery systems, aggregator agreements and other matters., In particular, with respect to battery systems, the Company plans to deliver them directly to developers and provide support. |
| Contract Date | 3 July 2026 |
| Alliance start date | 3 July 2026 |
| Impact on Business Performance | The Company expects this business alliance to have a minor impact on its results for the current fiscal year (the fiscal year ending June 2027). |
Items this document does not state (14)
These are items the company does not state in this document. We do not leave them blank, nor fill them in from other sources or by inference.
The reasons the company gives
The company's own explanation, not something inferred from the numbers.The grid-scale battery storage market is expanding against the backdrop of the transition to a decarbonized society and the need to secure flexibility for balancing electricity supply and demand. In addition, the Company will participate in the special high-voltage-scale battery plant business to expand the scope of its battery business.